I have a mimic of the Vantage Time Phase report I wrote in crystal for
6.1
I would be curious to have a look at yours to do some comparisons and
see if there is extra value I could get out of it. I would be willing to
swap reports with you. You should easily enough be able to update mine
to V8 with minor changes to fields based on V8 schema/table structure
change. Also my report has a formula for suggestions that may be the
solution to your question below.
________________________________
From: Charles Carden [mailto:shadowcar1449@...]
Sent: Saturday, October 25, 2008 6:14 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Re: Time Phase Report To Excel In 8.03.305
The part detail table is updated immediately and does not require MRP to
run.
It is easy enough to write a time phase in Crystal. I created a BAQ
using the following tables:
Part - filtered for only Quantity Bearing Purchased Parts
PartPlant - Buyer Id and Default Supplier and MRP Parameters
PurAgent - Buyer Name
Vendor - Default Supplier ID and Name
PartDtl - Demand and Purchases
JobHead - Part Revision
SugPOChg - Purchase Order Info
PartWhse - On Hand Quantity
JobProd - Order Number if Demand comes from an Order
I provided filters by Buyer ID and Part Number. This is what the buyers
are always looking for. The report can still be lengthy for a single
buyer but it is much better than the thousands of pages that are printed
with the standard MRP report. I was unable to show the new PO
suggestions on the report because of table linkage issues. If anyone has
figured out how to include the new suggestions I would be very
interested in how it was done. The change suggestions table is the only
one that does require MRP.
I also allowed a cutoff date option for the report since we run MRP out
9 months but the buyers are not always wanting to look that far in the
future. I would liked to have provided an option to only include parts
with exceptions but I couldn't figure that one out either. I did
calculate an order by date for the parts that dropped below zero on the
report. This was tricky because I had to look at the receive time and
lead times and then had to ensure that I counted back only working days
and then come up with an order date that was not on the weekend. I
probably should have used the calendar file for the Vendor to come up
with working days but since we only have one calendar I decided against
it.
The report was sorted by Buyer ID/Part Number.
Charles Carden
IT Manager
Manitex, Inc.
6.1
I would be curious to have a look at yours to do some comparisons and
see if there is extra value I could get out of it. I would be willing to
swap reports with you. You should easily enough be able to update mine
to V8 with minor changes to fields based on V8 schema/table structure
change. Also my report has a formula for suggestions that may be the
solution to your question below.
________________________________
From: Charles Carden [mailto:shadowcar1449@...]
Sent: Saturday, October 25, 2008 6:14 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Re: Time Phase Report To Excel In 8.03.305
The part detail table is updated immediately and does not require MRP to
run.
It is easy enough to write a time phase in Crystal. I created a BAQ
using the following tables:
Part - filtered for only Quantity Bearing Purchased Parts
PartPlant - Buyer Id and Default Supplier and MRP Parameters
PurAgent - Buyer Name
Vendor - Default Supplier ID and Name
PartDtl - Demand and Purchases
JobHead - Part Revision
SugPOChg - Purchase Order Info
PartWhse - On Hand Quantity
JobProd - Order Number if Demand comes from an Order
I provided filters by Buyer ID and Part Number. This is what the buyers
are always looking for. The report can still be lengthy for a single
buyer but it is much better than the thousands of pages that are printed
with the standard MRP report. I was unable to show the new PO
suggestions on the report because of table linkage issues. If anyone has
figured out how to include the new suggestions I would be very
interested in how it was done. The change suggestions table is the only
one that does require MRP.
I also allowed a cutoff date option for the report since we run MRP out
9 months but the buyers are not always wanting to look that far in the
future. I would liked to have provided an option to only include parts
with exceptions but I couldn't figure that one out either. I did
calculate an order by date for the parts that dropped below zero on the
report. This was tricky because I had to look at the receive time and
lead times and then had to ensure that I counted back only working days
and then come up with an order date that was not on the weekend. I
probably should have used the calendar file for the Vendor to come up
with working days but since we only have one calendar I decided against
it.
The report was sorted by Buyer ID/Part Number.
Charles Carden
IT Manager
Manitex, Inc.
----- Original Message -----
From: nmtaylor1969
To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
Sent: Saturday, October 25, 2008 1:23 AM
Subject: [Vantage] Re: Time Phase Report To Excel In 8.03.305
Thanks for that Gary, I had not spotted that, and I must say the data
in that table looks quite interesting. Its definitely the base data
for the timephase alright... :o)
Do you know if this data is updated in real-time, or does it get
updated when MRP is run...?
I had gone with my original plan and extracted the data via service
connect, and this works fine, however the data in the partdtl table
may well have lots of other uses for BAQ's and dashboards etc...
Nice one...
Many thanks,
Nick
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Gary Parfrey" <garyp@...> wrote:
>
> Nick, Rob
>
>
>
> Hope I got the whole thread. The timephase core dataset is in the
> partdtl table. We have rewritten the timephase report for
customers in
> the past in crystal.
>
>
>
> Gary Parfrey
>
>
>
> From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
[mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
Behalf
> Of nmtaylor1969
> Sent: 23 October 2008 16:01
> To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
> Subject: [Vantage] Re: Time Phase Report To Excel In 8.03.305
>
>
>
>
> Sorry, I'm on one now Rob...!
>
> If I have my timephase dataset in a format I can crunch/manipulate,
I
> can then produce the horizontal time phase ( i.e. a report that
> groups demand into weekly or monthly buckets ), dump this back into
> Excel, and use this as the main scheduling document with all my
> vendors...
>
> 8.03.305 does not appear to produce this report out of the box
which
> is most frustrating...
>
> If we have this, then we can run just about everything via KanBan,
> and practically turn the suggestions of all together... ;o)
>
> Nick
>
> --- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
<mailto:vantage%40yahoogroups.com> ,
> Robert Brown <robertb_versa@>
> wrote:
> >
> > Nick,
> >
> > Unfortunately - No. Time Phase not being a Crystal based report
> means their is no intermediate xml source you can read into excel
as
> a datasource.
> >
> > Since the data tables themselves are non-presistent temp tables,
> you can't even do a simple odbc poke query to bring the data into
> excel.
> >
> > I think you are on to something re: Service Connect's exposure of
> the timephase BOs & methods. That would at least trigger part by
part
> population of the temp data they generate. How you would then read
> them back out into a massive single data source (xml, csv) excel
can
> leverage is beyond my knowledge level at this time.
> >
> > Is it possible to invoke Service connect processing from within
> excel (via vbScript code)? Being excel/vbScript biased, that would
be
> my first attack plan attempt.
> >
> > You are 'one clever dude' Nick Taylor... Your posts consistently
> challenge & expand my thinking on ways to make this monstrousity
work
> for us instead of the other way around.
> >
> > Thanks
> >
> > Rob
> >
> > --- On Wed, 10/22/08, nmtaylor1969 <n.taylor@> wrote:
> >
> > From: nmtaylor1969 <n.taylor@>
> > Subject: [Vantage] Time Phase Report To Excel In 8.03.305
> > To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
<mailto:vantage%40yahoogroups.com>
> > Date: Wednesday, October 22, 2008, 3:56 PM
> >
> >
> >
> >
> >
> >
> > Has anybody found a way of getting the time phase report out to
> Excel ??
> >
> > We are struggling with managing purchasing suggestions, and this
> report
> > is useful, however Vantage produces this as a hardcopy report
> only... :o
> > (
> >
> > I know I can do this in ServiceConnect as the TimePhase
calculation
> is
> > available as a webservice, but before I run off and do that, I
> wondered
> > if anybody had found a quick way of getting it into Excel ??
> >
> > Thanks,
> >
> > Nick
> >
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]