If you want to use it to reorder parts from inventory using max, min & safety qtys
The report doesn’t work in E10.0.700.4, there is no fix for the report and Epicor says that it is fixed in E10.1
Gary Wojtowicz
AJR Industries, Inc.
If you want to use it to reorder parts from inventory using max, min & safety qtys
The report doesn’t work in E10.0.700.4, there is no fix for the report and Epicor says that it is fixed in E10.1
Gary Wojtowicz
AJR Industries, Inc.
The stock pars with show up but not the demand from the sales order because it’s flagged MAKE DIRECT.
As far as scheduling jobs and not following it. Welcome to manufacturing.
Patrick Winter
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Tuesday, March 08, 2016 08:01
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Time phase report Q's
So if I have a make direct order with some stock parts somewhere included, would those stock parts show up somewhere on the time-phase?
If we don't have a start, or due date that will screw it up too right? No one has set any of those yet.
Also, whenever we have seen the box "would you like to schedule the job?" we just say no because we know that we aren't using scheduling. Do we need to be scheduling the jobs even though we may not be following it?
If you add material to a job and don’t reschedule it, the material required date will be blank and you will see that in TimePhase as well.
I just added a part to a job without scheduling it. It does show up on the TimePhase report, but at the bottom with no date.
Miguel A. Santillan
Compass Manufacturing Systems
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Tuesday, March 8, 2016 6:18 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Time phase report Q's
The stock pars with show up but not the demand from the sales order because it’s flagged MAKE DIRECT.
As far as scheduling jobs and not following it. Welcome to manufacturing.
Patrick Winter
From:
vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Tuesday, March 08, 2016 08:01
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Time phase report Q's
So if I have a make direct order with some stock parts somewhere included, would those stock parts show up somewhere on the time-phase?
If we don't have a start, or due date that will screw it up too right? No one has set any of those yet.
Also, whenever we have seen the box "would you like to schedule the job?" we just say no because we know that we aren't using scheduling. Do we need to be scheduling the jobs even though we may not be following it?
This e-mail and any attachments may contain confidential and privileged information. If you are not the intended and/or named recipient or recipients, please notify the sender immediately by return e-mail, delete this e-mail and destroy
any copies. Any dissemination or use of this information by a person other than the intended recipient or recipients is unauthorized and may be illegal. Any views or opinions expressed in this email are those of the author and do not necessarily represent
those of the Specialty Screw Corporation. Warning: Although precautions have been taken to make sure no viruses are present in this email, Specialty Screw Corporation cannot accept responsibility for any loss or damage that may arise from the use of this email
or attachments.
This e-mail and any attachments may contain confidential and privileged information. If you are not the intended and/or named recipient or recipients, please notify the sender immediately by return e-mail, delete this e-mail and destroy any copies. Any dissemination
or use of this information by a person other than the intended recipient or recipients is unauthorized and may be illegal. Any views or opinions expressed in this email are those of the author and do not necessarily represent those of the Specialty Screw Corporation.
Warning: Although precautions have been taken to make sure no viruses are present in this email, Specialty Screw Corporation cannot accept responsibility for any loss or damage that may arise from the use of this email or attachments. ÂÂ
Disclaimer
The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or taking action in relation of the contents of this information is strictly prohibited and may be unlawful.
In my case, even though I did not schedule the job, it still showed up on the report, but on the bottom with no date.
Miguel A. Santillan
Compass Manufacturing Systems
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Tuesday, March 8, 2016 1:20 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Time phase report Q's
If you add material to a job and don’t reschedule it, the material required date will be blank and you will see that in TimePhase as well.
So if we never scheduled (much less REscheduled it) that's probably why stuff wasn't showing up on the report right? We just figured out some of this when stuff we need isn't being ordered. Fun.
Disclaimer
The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or taking action in relation of the contents of this information is strictly prohibited and may be unlawful.