Time phase of material assuming work order suggestion for parent part will be approved

Hi EpiUsers!

We have a manufactured part (embossed steel) that is required to manufacture a part on an order. Epicor suggests a work order to manufacture the embossed steel and that part’s time phased inquiry can be generated showing the impact of this suggestion.

However, the time phased inquiry of the material (smooth steel) required by the embossed steel’s MOM does not show the impact of that suggestion, until it is actually approved and turned into a work order and PO. Is there a way it could be shown while at the suggestion-stage?