Time Phase issue

I have a part that when I run MRP come up with suggestions and a unfirm job.

When I turn off suggestions the unfirm job is still there. I am making 75k pieces due April 25 and the Sales Orders are for 2 release 1 for 50k in May and the other is 225K in November. All of this is for 2023. I had expected MRP to see the 75k in May and not create an unfirm job. Is there a setting or am I missing something.

The job quantity probably isn’t locked, so MRP is suggesting you reduce your firm job quantity and make it closer to the due date. If you lock the job quantity, then rerun MRP on regenerative, the unfirm job should go away.

Thank you. I totally forgot about that.