This is an issue for us. I am not sure why it was changed. We have a report
builder report that has set up and production broken out by workcenter. But
it would be much nicer to have it done in the shop load report.
Thanks,
Judy Stauduhar
Taber Bushnell/Lake Air Metal Stampings
judys@...
Subject: Shop Load Report
Question on scheduling
Prior to version 3.0, the Vantage Shop Load report included an option to
break
out Setup and Production hours. In version 3.0, this option was removed.
This
option was valuable to us since skilled setup labor is often a scheduling
bottleneck. I'm curious if this has been an issue for other Vantage users?
If is has been an issue what tools have you used to replace this once
available
feature? Report Builder? Customization?
Any feedback would be much appreciated!
Thanks,
Mike Lowe
Connor Manufacturing Services
(909) 273-1282
MLowe@...
builder report that has set up and production broken out by workcenter. But
it would be much nicer to have it done in the shop load report.
Thanks,
Judy Stauduhar
Taber Bushnell/Lake Air Metal Stampings
judys@...
Subject: Shop Load Report
Question on scheduling
Prior to version 3.0, the Vantage Shop Load report included an option to
break
out Setup and Production hours. In version 3.0, this option was removed.
This
option was valuable to us since skilled setup labor is often a scheduling
bottleneck. I'm curious if this has been an issue for other Vantage users?
If is has been an issue what tools have you used to replace this once
available
feature? Report Builder? Customization?
Any feedback would be much appreciated!
Thanks,
Mike Lowe
Connor Manufacturing Services
(909) 273-1282
MLowe@...