Thanks to everyone for your input. I now have enough information to
take the correct actions. Thanks!
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Claudia J Stone
Sent: Wednesday, October 31, 2007 2:59 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Standard Cost
The average cost is a weighted average of all receipt costs for a
specific part. This cost is recalculated every time you process a PO
receipt for a purchased item or a manufacturing receipt to stock from
a job.
The formula is (Previous On-Hand Quantity x Previous Unit Cost) +
(Receipt Quantity x Receipt Cost) / New Quantity On-Hand
This underlying business logic is the same in versions 5.2, 6.1 and
8.xx.
HTH
Claudia Stone
Aspacia Systems, Inc.
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Hernandez, Dolores" <dhernandez@...>
wrote:
Behalf
take the correct actions. Thanks!
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Claudia J Stone
Sent: Wednesday, October 31, 2007 2:59 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Standard Cost
The average cost is a weighted average of all receipt costs for a
specific part. This cost is recalculated every time you process a PO
receipt for a purchased item or a manufacturing receipt to stock from
a job.
The formula is (Previous On-Hand Quantity x Previous Unit Cost) +
(Receipt Quantity x Receipt Cost) / New Quantity On-Hand
This underlying business logic is the same in versions 5.2, 6.1 and
8.xx.
HTH
Claudia Stone
Aspacia Systems, Inc.
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Hernandez, Dolores" <dhernandez@...>
wrote:
>was
> Our material manager was under the assumption that the average cost
> partly determined by the standard cost and because the standardcost are
> not correct, the average cost was incorrect.[mailto:vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ] On
>
> So how is the average cost determined? And we are using the average
> cost method.
>
>
>
> ________________________________
>
> From: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
Behalf
> Of Mark Wonsilthe
> Sent: Wednesday, October 31, 2007 12:01 PM
> To: vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com>
> Subject: RE: [Vantage] Standard Cost
>
>
>
> Just to add to Scott's remarks:
>
> > Standard Cost are completely manually set.
>
> Standard costs can be set manually using Cost Adjustment or through
> Costing Workbench when doing a Cost Roll Up, which isan "automatic" way
> tofields.
> manually set the standard cost.
>
> ;-)
>
> I was told that Vantage always calculates every cost method but only
> uses the
> one that is set on the Part Plant record for the given plant. If the
> method is
> average, it really shouldn't matter what is in the standard cost
>[Non-text portions of this message have been removed]
> Mark W.
>
>
>
>
>
> [Non-text portions of this message have been removed]
>