Hi Brad,

We do have that situation because we have warehouse employees that do not book time to jobs but often do not clock out. I will clean these guys out regularly now and see if that helps…

Thanks,


Neil Buckman
Information Technology

[Gibson Shopfitters]

DH Gibson Pty Ltd | 205-231 Fairfield Rd | YENNORA NSW 2161
Office 8724 4600 | Direct 8724 4618 | Fax 8724 4604 | Mobile 0413 125 994
nbuckman@...<mailto:nbuckman@...> | www.gibsonshopfitters.com.au <http://www.gibsonshopfitters.com.au/>




From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Thursday, 12 June 2014 10:26 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Speeding up MES End Activity - 9.05.700C



Neil,



We have watch our clock outs. If someone stays clocked in for days or weeks on end the whole MES system slows to a crawl like that. We use shop tracker to go in an look who is clocked in an since when.



FYI



Brad Boes

Metalworks



Notice:This e-mail and any attachments are confidential and are only for the use of the person to whom they are addressed. If you are not the intended recipient please advise the sender by return e-mail and delete the message and any attachments. Any use, interference with, disclosure or copying of this message or any attachments is unauthorised and prohibited. The sender does not warrant that the information is free of a virus or any other defect or error, and any views expressed herein, unless specifically indicated otherwise, are those of the individual sender.

The DH Gibson Group of Companies - http://www.gibsonshopfitters.com.au

P Please consider our shared environment before printing this communication.



[Non-text portions of this message have been removed]

 

We are seeing longer delays on the End Activity function in MES.  When a number of people are wanting to complete their activity at the end of the day it is taking minutes to end each one and clock off the user.  When multiple work stations are used at the same time we can get an "Unexpected error" message.

 

Any suggestions as to how this can be speeded up?

 

 - Neil

 

 

Neil,

 

We have watch our clock outs. If someone stays clocked in for days or weeks on end the whole MES system slows to a crawl like that. We use shop tracker to go in an look who is clocked in an since when.

 

FYI

 

Brad Boes

Metalworks

Thanks Patrick,

Yes there is one and I have created now a tighter condition so that it fires less often. Hopefully that will help.


Neil Buckman
Information Technology

[Gibson Shopfitters]

DH Gibson Pty Ltd | 205-231 Fairfield Rd | YENNORA NSW 2161
Office 8724 4600 | Direct 8724 4618 | Fax 8724 4604 | Mobile 0413 125 994
nbuckman@...<mailto:nbuckman@...> | www.gibsonshopfitters.com.au <http://www.gibsonshopfitters.com.au/>




From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Thursday, 12 June 2014 10:38 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Speeding up MES End Activity - 9.05.700C


Any data directives on labor detail or labor head records?

Patrick

From: vantage@yahoogroups.com<mailto:vantage@yahoogroups.com> [mailto:vantage@yahoogroups.com]
Sent: Wednesday, June 11, 2014 23:35
To: vantage@yahoogroups.com<mailto:vantage@yahoogroups.com>
Subject: [Vantage] Speeding up MES End Activity - 9.05.700C





We are seeing longer delays on the End Activity function in MES. When a number of people are wanting to complete their activity at the end of the day it is taking minutes to end each one and clock off the user. When multiple work stations are used at the same time we can get an "Unexpected error" message.



Any suggestions as to how this can be speeded up?



- Neil







Notice:This e-mail and any attachments are confidential and are only for the use of the person to whom they are addressed. If you are not the intended recipient please advise the sender by return e-mail and delete the message and any attachments. Any use, interference with, disclosure or copying of this message or any attachments is unauthorised and prohibited. The sender does not warrant that the information is free of a virus or any other defect or error, and any views expressed herein, unless specifically indicated otherwise, are those of the individual sender.

The DH Gibson Group of Companies - http://www.gibsonshopfitters.com.au

P Please consider our shared environment before printing this communication.



[Non-text portions of this message have been removed]