We have a scenario with two sites: SITE1 and SITE2.
- Finished Product: A manufactured item with a subcontract operation and one material.
- Material: Used in the BOM for the subcontract operation. Needs to:
- Be purchased for subcontracting and delivered directly to SITE2.
- Have stock held at SITE1 for use in other parts.
We want to do the following:
- Maintain minimum stock levels at SITE1.
- When stock at SITE1 falls below minimum:
- MRP: Create a subcontract job on SITE1 with materials sourced from SITE2.
- PO Suggestions: Generate at SITE2 to order and deliver materials to SITE2 if needed.
- Subcontract PO: Created at SITE1 for the finished part.
Is there a way to configure Kinetic to handle this process automatically? Any advice or solutions are appreciated!