Skip printing completed operation Job Traveler

Hi all,

Is there a way to skip completed operations when re-print a job traveler?

For example, if opr 5 is completed, ideally we only want to print opr 10 on the job traveler to avoid any confusion on the shop floor.

Thanks,
Dan

Try applying the following filter on the OprSeq Group :

1 Like

Thank you very much! Worked like a charm!