Looking for some advice on how to schedule subassemblies to start on different days (1 and 2 days before my first operation of the Method starts) automatically when job created with part
For instance
Day 1 | SubAssy01 starts| Related: Operation 040
Day 2 | SubAssy02 starts| Related: Operation 010
Day 3 | Operation 010 starts
Any help would be appreciated. Also just a helping hand where to look in the manual etc.
Try using the receive time which is at part>site>planning
or change the scheduling relation between two subsequent
. There are three options:
Start-to-Start – The application schedules one operation to start as soon as the previous operation begins.
Finish-to-Finish – The application schedules one operation to finish at the same time that a previous operation finishes.
Finish-to-Start – The application schedules one operation to begin as soon as the previous operation ends.
The scheduling option you select here is not used across all the assemblies. Select the scheduling options you need on each operation.
Tip: The first operation on each assembly is always treated as finish-to-start. The operation Start Date is based on the Due Date from the last operation on a previous assembly.