Anyone else out there manually updating multiple production calendars for non-productive days because your holiday calendars came out for next year… even though you own the DMT?
In the classic UI, you can ctrl+click multiple days if you’re in the ‘year’ view. When you click toggle, they all get set. You can change to the next calendar in the left column, not lose the selected days, and toggle. I got it done pretty quickly across 12 calendars. The exception days will have a slightly bolded font.
Anyone want to bet that the Classic UI is faster than the Kinetic UI, start to finish? I’ll race ya!