In job entry, click on "lock quantity" and also on "lock schedule".
This will prevent suggestions from occurring.
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Joel Kolling
Sent: Monday, August 03, 2009 1:47 PM
To: vantage@yahoogroups.com
Subject: [Vantage] prevent MRP from making suggestions
Our Manufacturing manager has a question for the group:
Is there a way to prevent MRP from making suggestions (like date or qty
change) to jobs that you have already firmed and released? I would like
it to just generate a whole new job instead trying to change the one
already released.
AriAnne Sproat
ITC Manufacturing
Office: 602-415-1400 Ext. 228
Mobile: 602-909-9644
Fax: 602-415-1444
Email: arianne@... <mailto:arianne%40itcmfg.com> <mailto:
arianne@... <mailto:arianne%40itcmfg.com> >
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
This will prevent suggestions from occurring.
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Joel Kolling
Sent: Monday, August 03, 2009 1:47 PM
To: vantage@yahoogroups.com
Subject: [Vantage] prevent MRP from making suggestions
Our Manufacturing manager has a question for the group:
Is there a way to prevent MRP from making suggestions (like date or qty
change) to jobs that you have already firmed and released? I would like
it to just generate a whole new job instead trying to change the one
already released.
AriAnne Sproat
ITC Manufacturing
Office: 602-415-1400 Ext. 228
Mobile: 602-909-9644
Fax: 602-415-1444
Email: arianne@... <mailto:arianne%40itcmfg.com> <mailto:
arianne@... <mailto:arianne%40itcmfg.com> >
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]