Hello,
I was asked an interesting question. Engineering would like to have a maintenance plan for the equipment to be setup as : Perform the maintenance every 6 months OR every 50000 cycles. Which ever comes up first.
Documentation indicates :
Each plan you create represents a preventative maintenance procedure that needs to be completed on the item; for example, oil changes, filter replacements, belt changes, and so on. You can designate the preventative maintenance plan as time- or meter-based. I noticed I was able to enter both setups.
I added 6 months and 50000 for the meters.
- Can this be setup within the same plan? if I setup the date section and the meter section
if so, does the date will change to the next 6 months after the maintenance is done, if it was trigered via meters? And vice-versa meters will be added 50000 if it was trigered by time?
The goal here is if the meter generated the maintenance within a month of the time limit of 6 months, I would not want to generate a new job trigered by the 6 months setup!
Anyone using it this way?