In an effort to combine all our suggestions into single order suggestions I have set the days of supply, planning time fence, reschedule out time delta, and the reschedule in time delta. The days of supply combined the individual order suggestions and the others cleaned up the messages. However, as Ken mentioned in his response, the system is still suggesting to buy which can cause overbuying if change suggestions are not being monitored.
--- In vantage@yahoogroups.com, Karl Dash <dashkarl@...> wrote:
>
> Have you looked at Days of Supply on the Part/Plant table in order to consolidate deliveries and avoid repetitive smaller deliveries?
>
> -Karl
>
>
>
>
> ________________________________
> From: Ken Williams <kwilliams@...>
> To: "vantage@yahoogroups.com" <vantage@yahoogroups.com>
> Sent: Thu, May 6, 2010 7:05:35 AM
> Subject: RE: [Vantage] Re: PO Suggestions and Time Phased - Bayesian Filter detected spam
>
> ÂÂ
> Are they reviewing both new & change suggestions?
>
> Are they viewing Time Phase with "suggestions" checked?
>
> From: vantage@yahoogroups .com [mailto:vantage@yahoogroups .com] On Behalf Of bturner101@sbcgloba l.net
> Sent: Thursday, May 06, 2010 7:59 AM
> To: vantage@yahoogroups .com
> Subject: [Vantage] Re: PO Suggestions and Time Phased - Bayesian Filter detected spam
>
> We have tried this and still purchasing was not satisfied. It did clean up some noise but it wasn't enough for each buyer to trust PO suggestions.
>
> --- In vantage@yahoogroups .com<mailto:vantage% 40yahoogroups. com>, "bw2868bond" <bwalker@ > wrote:
> >
> > We lock the PO Release quantity to keep MRP suggesting cancel and re-order noise to a minimum. V8.03.405a
> >
> > --- In vantage@yahoogroups .com<mailto:vantage% 40yahoogroups. com>, "bturner101@ " <bturner101@ > wrote:
> > >
> > > Forgive me for any ignorance about the system I may have in my following question.
> > >
> > > We are currently running version 8.03.407.
> > >
> > > Our procurement has brought PO suggestion inconsistencies to my attention and I can not figure out how to fix it. If there is a fix. The system seems to be working off Just in Time principles. For instance, the system continues to suggest purchasing materials we do not need based on demand and Job due dates. When we look into this further, we noticed Time Phased is suggesting to cancel PO orders and recreate the order with a due date that will satisfy the Job material requirement.
> > >
> > > The system is assuming that a PO due date can be moved in on a new PO to satisfy the supply requirements. The problem is PO suggestions does not show any of this information, it only tells you to order more. Thus the suggestion screen is filled with supply we don't need and our purchasers are spending most of their time verifying PO suggestions rather than maintaining our supply.
> > >
> > > Is there any way to tweak the system to prevent this from happening?
> > >
> > > Any help would be greatly appreciated.
> > >
> >
>
> [Non-text portions of this message have been removed]
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>