Parts - Detail - Constrained material

Hi

10.2.300

Under Part maintenance > Detail - Constrained material.

I am not sure what is affected when adding this check mark (move time, lead time…etc).
I try different tests and on the scheduling board I am not seeing the difference.

thanks for your help

Philippe

It affects the start date of the job. MRP considers the lead time or due date of the PO of the part when scheduling the job to calculate the start date.

Hi Jay

Thanks for the info.
This section I understand.
What I am looking for is which field (Ex Lead time) will affect the scheduling when the material constraint is checks.

Philippe

The leadtime field under purchasing

Thanks Jay

it work.

philippe