Good morning,
I’m fairly inexperienced with Epicor and capabilities, I’ve only been lightly using it for roughly a year now.
We’re working through a more recent issue with a specific customer where the they order a top level part number with various options. I know good manufacturing practices would be to have a new part number for each option set but I’m curious if there is another way to handle that with in Epicor’s part number structure.
Is there a way to setup options to a top level part number without creating additional top level part numbers to capture all the option combinations? We have no control over which option sets are ordered. It could be one, two, or even all five or more for the top level.
Thank you,