Mtl in Inspection bypasses MRP

Your buyrs/planners can see the uninspected (or failed inpected & pending DMR disposition) in that non nettable state in Time Phase.
Teach them to pick up phone and find out what is going on. Before acting. - knowing it nay take days (even weeks) to determine diposition path.
If they are kow cost parts you don't shutting down business (& a reorder s going to come from same suspect llot) - just order more..


--- Original Message ---
From:"michael.hutcheson@..." <michael.hutcheson@...>
Sent:Tue 10/26/10 9:17 am
To:vantage@yahoogroups.com
Subj:[Vantage] Mtl in Inspection bypasses MRP

Hello,

We have an issue where when material is in inspection, MRP bypasses it. The non-nettable is against the bin is unticked but this is still a problem, any ideas?

Regards,

Michael

Vantage 8.03.406
Hello,

We have an issue where when material is in inspection, MRP bypasses it. The non-nettable is against the bin is unticked but this is still a problem, any ideas?

Regards,

Michael

Vantage 8.03.406