MRP Planning Horizon

,

Is the only way to set the MRP Planning Horizon (the time frame that MRP looks out into the future for demand) by using the Cut Off Date in MRP Processing? The longest horizon I see there is end of month plus 12 and we have component lead times longer than that.

Try entering this in the MRP Cut off Date to get further out from the run date.

&Today+250
Replace 250 with the # of days you need

Credit @Banderson

1 Like

Additionally, you can leave the field empty and it will go as far out as 10 years, I believe.