Although I am still working in Test Vista and we are currently using the classic system, I am doing milestone billing.
When I send out milestone billing it becomes advance money and a liablity. My projected sales still include this amount because the sale has not been realized. If you took it off the sales report you would have to use it for tax purposes.
I think this is correct the way I understand it.
Pam
When I send out milestone billing it becomes advance money and a liablity. My projected sales still include this amount because the sale has not been realized. If you took it off the sales report you would have to use it for tax purposes.
I think this is correct the way I understand it.
Pam
--- In vantage@yahoogroups.com, "jplehr" <jlehr@...> wrote:
>
> Vantage 8.03.406
>
> Looking for anyone using Milestone (Advanced) Billing.
>
> I am beginning to work with the idea of using Project Entry and setting up milestones for billing purposes. This is all very new to me, so here is the firt of what will probably be many questions. I am relaying this second hand so I hope it makes sense.
>
> I was able to work through the process that triggered the milestone to be invoiced. This worked nice so that I was able to invoice without affecting a shipment. I expected that my Sales Backlog Report would not be affected and the dollars would still show since I had not shipped.
>
> However, the issue comes when management runs the Sales Backlog Report to see what dollars are available for shipment within the given month and the dollars, that were previously invoiced (not shipped), are still listed on the report. We understand that the Milestone Billing defaults as 'Deferred Revenue', which was unchecked because we wanted the sale at the time of invoice. The Sales Order Backlog Report leads management to believe we still have those dollars coming.
>
> Management wants to see what dollars are available less this item that was invoiced in advance. Is this possible? Is this a good business practice?
>
> Jeff
>