I create Job# A-1000 and I want to produce 1000 of Part A
Is there any way to ‘telling’ the system that I have now produced 1000 units of Part a without doing a Time/Labor entry?
I create Job# A-1000 and I want to produce 1000 of Part A
Is there any way to ‘telling’ the system that I have now produced 1000 units of Part a without doing a Time/Labor entry?
Where do I find that?
In classic MES on the production tab. In Kinetic MES on the Production page in the Apps section.
Well… I don’t have MES.
.
..
Sorry, I don’t know of another way to complete jobs.
Try Job Adjustment (under Job Management / General Operations)
Take a look at kanban jobs and see if they will work for you.
Another place is Time and Expense Entry.