Is there a way to get the work que to fill the Labor QTY box when complete is clicked? Our setup will allow us to hit complete, but it does not enter the number that would equal complete, and often then does not backflush materials.
Also - Is there a way to have the work que NOT show resources that are inactive?
That explains it, thank you, was not thinking of that.
I believe there are some posts on here about hiding inactive records in screens like that.
What I usually do in these instances is create a Resource Group that is for Inactive Resources and when a resource is made inactive, I move the resource there.