Locking Subcontract Jobs Due Dates

Hi all,

Is there a way in Epicor 10 to “lock date” for Subcontract jobs? Epicor wants expedite Subcontract jobs but I know it cannot happen per the Vendor.

I know one can lock date on Purchase Orders and that effectively gets rid of the expedite (or postpone) Epicor message.

Thanks in advance!

Luke

Once a job is scheduled you can “lock” the job to the schedule so that the system does not reschedule operations during global scheduling. Just open the job in job entry, and look for the scheduling section and click “Lock” This will keep the operation dates in place. If you have to change an operation date, just unlock the job and change the schedule, then relock it.

Nate,

Thanks for your response and the info! I have locked a few jobs to test and see if that inhibits E10’s expedite/postpone job suggestions.