Zerobertson
(Zachary Robertson)
1
We have a situation when looking at a job where the clock in time is 50 mins. Clocked in 22:56 and Clocked out of 23:46.
This is the only labor transaction for the operation on the job but the Labor Hours are showing 13.99.
In what type of situation can this occur?
jkane
(John Kane)
2
Someone could have done a Job Adjustment.
Someone might have gone into Time & Expense entry and manually entered the 13.99 without adjusting the clock in and out.
Zerobertson
(Zachary Robertson)
3
It seems we don’t have any changelog’s created for that as well and the job is from 2020. Is there any way to know otherwise?
jkane
(John Kane)
4
You can pull up the record in Time and Expense and see what is there.
Zerobertson
(Zachary Robertson)
5
Not 100% sure this is the actual solution but all signs are indicating that probably was the case.