The problem were having is trying to identify how:
If 1 employee works on various different jobs OR machines (at the same time), how does epicor apportion his time?
AND is this apportionment fixed or can it be changed?
Reading other forums - they point to resource group setup.
If the logic is the same in E9 as it is in e10 (and I don’t know if it is), then it looks at the labor standard (est time) on the operation and splits out the labor using that as a weight. For example, if Operation A has a standard of 9 hours, and operation B has a standard of 1 hour, and the worker is clocked into both for 5 hours, it will apply 4.5 hours to Operation A and .5 to Operation B. If you don’t have labor standards in place, then there is no weight applied and it will just apply them 50/50.