When adding operation details in Job Entry the Labor Method defaults to Time and Quantity. Need to set the Labor Method depending on the Operation selected. Some Operations use Time and Quantity others use Quantity only. Has anyone done this and how was it accomplished. Any assistance would be gratefully received.
It defaults Time and Quantity based on the data dictionary. You can change this to be what most of your operations are and the manually changed what isn’t. You could also create a BPM to default based on conditions relating to the operation, ie user defined field T, Q or B etc.
I’d agree a BPM, what options are available in the plant config. As Paul said you would need to define the Labor method for each of your Operations and go from there.