Hi,
I have an updatable BAQ/dashboard where I want to be able to change the due date of the job.
Normally, this is done via Job Entry where the user unticks “Engineered”, makes the changes, ticks “Engineered”, saves it, and then writes the change description in the Change Audit Log popup window.
On the dashboard, I can untick “Engineered”, save it and refresh dashboard, and then change the due date and save it. but when I try to tick “Engineered” and save it, the changes do not get saved and i cannot write a new Change Audit Log description. I can only modify the last Audit log displayed in the dashboard.
Is it possible to make changes to a job in the dashboard and then tick “Engineered” where the Change Audit Log pops up before saving the changes?
Regards
Himal
HG_JobUpdate3-1.baq (42.7 KB)