Job Tracker, Green Checks and Setup Activities

We like the green check visual indicator in the Job Tracker tree that shows if an operation in the job has been marked complete.

image

We are talking about starting to record Setup Activities in addition to production. I noticed if I record a setup activity on a job, report 100% of the setup complete, and mark the ‘Complete’ checkbox, job tracker will have the green check on that operation, indicating it is complete.

Is this just the way it is or am I missing something?