Sure. Send it to ross(dot)hughes(at)comcast.net
Ross
-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Marty
Sent: Thursday, April 23, 2009 9:17 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Job Efficiency % on Production Detail Report
Ross
Can I e-mail you the Production Detail Report I am looking at if you have
time to review it to see what I might be doing wrong to verify the vantage
Eff #.
If yes what e-mail address should I send it to
Marty
Ross
-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Marty
Sent: Thursday, April 23, 2009 9:17 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: Job Efficiency % on Production Detail Report
Ross
Can I e-mail you the Production Detail Report I am looking at if you have
time to review it to see what I might be doing wrong to verify the vantage
Eff #.
If yes what e-mail address should I send it to
Marty
--- In vantage@yahoogroups.com, "Ross Hughes" <ross.hughes@...> wrote:
>
> I can believe that.
>
> I am only trying to point to where the calculation is coming from in the
> Production Detail report that he is wrestling with.
>
> Ross
>
> -----Original Message-----
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of
> Todd Caughey
> Sent: Thursday, April 23, 2009 8:33 AM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] Re: Job Efficiency % on Production Detail Report
>
> Earned Hours can be off too (in 6.10 anyway). Many times when I manually
> calculate it using the exact formulas given it will not match the value on
> the Labor Detail. Working with Support our best guess was something in
> Labor Edit was depositing incorrect info. But I had many cases where the
> Earned Hours manually calculated should have been 8 hours and the value in
> the system was randomly wrong...like 14.3 hrs, even when the quantity
> produced was almost exactly as estimated. Since it was easy enough to
> calculate it myself (and 6.10 will never be patched again) I just stopped
> using the value in the system. I hope this has been fixed in later
versions
> but since it was never acknowledged as a bug it probably wasn't..
> -Todd C.
>
>
> ________________________________
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of
> Ross Hughes
> Sent: Thursday, April 23, 2009 8:16 AM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] Re: Job Efficiency % on Production Detail Report
>
>
>
>
> You may want to look in to earned hours. Although the report may not
> display this in the detail the formula at the bottom is calculating from
> this and this is a hidden field in the report.
>
> Here are the earned hour calcs:
> -------------------------------------
> For Production:
>
> If the Run quantity > 0: EarnedHrs = EstProdHours / RunQty x LaborQty
>
> If the Production Standard is fixed hours: EarnedHrs <= EstSetHours -
> ActSetHours + SetReworkHours - Burden Hours for this labor detail record
>
> If the operation quantity = 1: EarnedHrs = Operation Hrs Remaining
> (EstProdHours - ActProdHours) or Hours Worked (BurdenHrs), whichever is
less
>
> For Setup:
>
> Setup Not Complete: EarnedHrs = EstSetHours x SetupPctComplete or
> ActSetupHours, whichever is less
>
> Setup Complete: EarnedHrs = EstSetHours - ActSetHours + SetReworkHours -
> Burden Hours for this labor detail record
> ------------------------------------
> Do this math on the detail and then see if the numbers make more sense.
>
> Or provide more detail and I can try to help with the calculations. Your
> labor detail records should have the earned hours in them as they are
> calculated through the business logic.
>
> Ross
>
> -----Original Message-----
> From: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>
> [mailto:vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>] On
Behalf
> Of
> Marty
> Sent: Thursday, April 23, 2009 7:32 AM
> To: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>
> Subject: [Vantage] Re: Job Efficiency % on Production Detail Report
>
> Let me line up the hours better..when I used preview it looked ok the
first
> time I posted it
>
> Estimated Hours
>
> Setup __ 1.80
> Prod __ 0.49
>
> Actual Hours
> Setup __ 0.42
> Prod __ 0.93
>
> Eff. Pct: 54.15
>
> I can't figure out where the 54.15 is coming from..
>
> This is at the end of the report just about the Profitability Area of the
> report
>
> --- In vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>, "Marty"
> <marty1325@> wrote:
> >
> > I also thought it might NOT be using Setup to calculate the percentage
but
> that didn't work either..
> >
> > Here are the #'s I am seeing on my Report (at end of report where I
assume
> its recaping the detail hours)
> >
> > Est Hours Actual Hours
> > Setup 1.80 .42
> > Prod .49 .93 Eff Pct: 54.15
> >
> > I am Sooo Confused...
> >
> > thanks.
> >
> > Marty
> >
> >
> >
> >
> > --- In vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>, Robert
> Brown <robertb_versa@> wrote:
> > >
> > >
> > > Look at LaborDetail to see if there is an estimate cost versus actual
> cost bucket (not hours). It could be doing dollar math (and actual dollars
> aren't always one to one with hours if you split burden, etc,).
> > >
> > > Another crazy possibility: Set up is non-value added cost. See if the
> %'s add up with set up left out.
> > >
> > > ???
> > >
> > > Rob
> > >
> > > --- On Wed, 4/22/09, Marty <marty1325@> wrote:
> > >
> > > From: Marty <marty1325@>
> > > Subject: [Vantage] Job Efficiency % on Production Detail Report
> > > To: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>
> > > Date: Wednesday, April 22, 2009, 4:11 PM
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > >
> > > I am trying to figure out how vantage Calculates this # at the end of
> the Production Detail Report.
> > >
> > > The Heading is ASM Totals (job # after it)
> > >
> > > I am not talking for each of the operations. But at the end of the
> report where it says Estimated Setup and Production Hours and next to it
> Actual Setup and Production hours are listed
> > >
> > > One would think all you would do is to add the Estimated Setup and
> Production Hours and divide by the Actuals.
> > >
> > > But NO...I can't get it to even come close doing it that way.
> > >
> > > What Vantage logic am I missing here.
> > >
> > > Thanks....
> > >
> >
>
> ------------------------------------
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
> already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder and
> Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
>
>
> ------------------------------------
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have
> already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder and
> Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links
>
------------------------------------
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links