Job Adjustments for Backflush Ops

Rob, thanks for the input/idea.

I might not have to do this, but I tested it and it works; I changed the Entry Method to "Qty-Only", made my adjustment and reverted to "Backflush". I did not go further with the test on what costing impact would have or how my GL is affected but, mechanically it worked.

Thanks again Rob.

Roel Martinez
ERP Analyst

SABRE TUBULAR STRUCTURES (tm)
www.sabretubularstructures.com<http://www.sabretubularstructures.com/>
8653 E. Hwy 67 | Alvarado, TX 76009
Phone: 817-852-1700 ext. 11858 | Direct Line: 817-852-1858 |Fax: 817-852-1705


From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of robertb_versa@...
Sent: Wednesday, September 22, 2010 1:09 PM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Job Adjustments for Backflush Ops



Never tried adj parent OP to see impact on dependant BF OPs. (Curious to hear impact if you try).
Other option: Edit BF OPs to be Qty or Time & Qty, adjust, re-edit back to BF. (Might work?)
Rob

--- Original Message ---
From:"roelmartinez_sabreinudstries" <rmartinez@...<mailto:rmartinez%40sabre-sts.com>>
Sent:Wed 9/22/10 1:28 pm
To:vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>
Subj:[Vantage] Job Adjustments for Backflush Ops

Good afternoon all.

Just a quick question, hoping I am not off-base here. Vantage doesn't let me do a JobAdjustment for a Backflush Operation (don't know if I'm doing something wrong).... does this mean a JobAdjustment to the "parent" operation will adjust the backflushed one?

If not, how do I adjust labor for a Backflush Operation?

Thanks.
Roel Martinez



[Non-text portions of this message have been removed]
Good afternoon all.

Just a quick question, hoping I am not off-base here. Vantage doesn't let me do a JobAdjustment for a Backflush Operation (don't know if I'm doing something wrong).... does this mean a JobAdjustment to the "parent" operation will adjust the backflushed one?

If not, how do I adjust labor for a Backflush Operation?

Thanks.
Roel Martinez
Never tried adj parent OP to see impact on dependant BF OPs. (Curious to hear impact if you try).
Other option: Edit BF OPs to be Qty or Time & Qty, adjust, re-edit back to BF. (Might work?)
Rob

--- Original Message ---
From:"roelmartinez_sabreinudstries" <rmartinez@...>
Sent:Wed 9/22/10 1:28 pm
To:vantage@yahoogroups.com
Subj:[Vantage] Job Adjustments for Backflush Ops

Good afternoon all.

Just a quick question, hoping I am not off-base here. Vantage doesn't let me do a JobAdjustment for a Backflush Operation (don't know if I'm doing something wrong).... does this mean a JobAdjustment to the "parent" operation will adjust the backflushed one?

If not, how do I adjust labor for a Backflush Operation?

Thanks.
Roel Martinez