Issue with Rolling Standards in Epicor 10.2.100.8

Hello, I am trying to do my first cost roll in Epicor and am having an issue with rolling the costs. I have updated and posted all of the raw materials and when I am working with the finish goods, I have a problem seeing the new rolled cost that includes the new labor cost. I was able to get the updated labor in our test environment once but when I tried again with a new group and a different labor dollar, I am unable to see the different overall labor standard. I thought that maybe I had the steps in the wrong order but I have tried it so many times that I am not sure. First I Load the costs and bring them up, then I load the updated labor and roll the costs with the new labor and then I refresh the costs and pull them back in to view them and notice that the labor dollars did not change. Can anyone help, I would greatly appreciate it.

Lisa Nichols

I believe you need to avoid the refresh cost details step you mentioned as that pulls the costs back in from the partcost table.

After you roll the costs press the refresh button in the menu bar (not refresh cost details) to clear the grid then search button under manufactured parts screen again to pull the parts back into the grid. Your new labor cost should now be reflected. At this point I preview the cost set group report under actions and give it a quick glance to make sure there are no unexpected wild changes. The last step is to post the group which will actually post the cost adjustments.