Hello all, I have a process set running daily that has been in place longer than I have.
Every day at 0100 it runs:
- Auto Job Completion
- Auto Job Closing
- Process MRP
- Production Planning Process
We have never used the Production Planner Workbench as it is much too slow for our volume of jobs. We have a dashboard that shows the planner all jobs in the queue, and he sets the shop floor date and clicks “update”. This firms and releases the job and sets the Mass Print flag.
Does the Production Planning Process actually do anything? It takes an extra 15 minutes to run, and I’d like to trigger a job firming automation after MRP runs, in order to update negative available warnings on components before the buyers start their day.
Any thoughts?