The DMT tool would be useful for that purpose. What version are you on? Have you confirmed if that’s the expected behavior? Seems kinda sketchy to me.
Rob Bucek
Production Control Manager
D&S Manufacturing
301 E. Main St.
Black River Falls, WI 54615
715-284-5376 Ext. 311
Mobile: 715-896-3119
Visit our newly redesigned Website at www.dsmfg.com
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Wednesday, September 14, 2016 7:20 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Inactive Supplier
Good Morning,
We have many parts setup with supplier on part plant records. When a supplier gets made inactive, PO suggestions continue to get made for inactive supplier and unless we manually go through each part, each part continues to have incorrect supplier id.
What have others done to manage when they inactivate or unapprove a supplier, to get it to work throughout system? It would be nice to have a mass supplier replace program or something like that.