Global Scheduling gone wonky - Vista 8.03-409c

This has been happening for a couple a weeks. Calculate Global Scheduling did run normal. Priority codes have not been altered in any way.
Log file:
Wednesday March 14 15:53:41 2012

15:53:41 MRP finite scheduling process begin.
15:53:41 PID: 245996; Session: 10.50.100.7::MfgSys803::8301::912d80da97571a3f:a1807c:1358f17d60e:6d00
15:54:30 Starting Part Level: 0. Wait Time: 00:00:49, Jobs: 0
15:54:30 Scheduling new unfirm job:118074
15:54:32 The job is currently scheduled to finish 03/29/12. It will not meet its required date of 03/01/12.
15:54:32 Done Scheduling job:118074
15:54:32 Scheduling new unfirm job:118067
15:54:33 The job is currently scheduled to finish 03/23/12. It will not meet its required date of 03/01/12.
15:54:33 Done Scheduling job:118067
15:54:33 Scheduling new unfirm job:118071
15:54:35 The job cannot be scheduled for its requested date due to system setting
15:54:35 Done Scheduling job:118071
15:54:35 Scheduling new unfirm job:118095
15:54:35 The job is currently scheduled to finish 03/16/12. It will not meet its required date of 03/03/12.
15:54:35 Done Scheduling job:118095
15:54:35 Scheduling new unfirm job:118096
15:54:35 The job is currently scheduled to finish 03/16/12. It will not meet its required date of 03/03/12.
15:54:35 Done Scheduling job:118096
15:54:35 Scheduling new unfirm job:118097
15:54:36 The job is currently scheduled to finish 03/16/12. It will not meet its required date of 03/03/12.
15:54:36 Done Scheduling job:118097
15:54:36 Scheduling new unfirm job:118098
15:54:36 The job is currently scheduled to finish 03/16/12. It will not meet its required date of 03/03/12.
15:54:36 Done Scheduling job:118098
15:54:36 Scheduling new unfirm job:118032
15:54:38 The job cannot be scheduled for its requested date due to system setting
15:54:38 Done Scheduling job:118032
15:54:38 Scheduling new unfirm job:F-117267
15:54:40 The job cannot be scheduled for its requested date due to system setting
15:54:40 Done Scheduling job:F-117267
15:54:40 Scheduling new unfirm job:117900
15:54:42 The job cannot be scheduled for its requested date due to system setting
15:54:42 Done Scheduling job:117900
...
16:27:22 MRP process 101 done. Total Non Scheduling Time = 00:03:34. Scheduled Jobs: 1182 Deleted Jobs: 0 Save Load Jobs: 1182


The jobs that do not schedule are all for the same customer that had the receive time. It occured to me that if I lock those jobs the scheduler would ignore them. Would it resolve the issue (without actually solving the problem)?
Please bear in mind that I am a scheduler, not an IT person.
Georgia

--- In vantage@yahoogroups.com, Rob Bucek <rbucek@...> wrote:
>
> How long has this persisted? Just the last run or several runs? Can you verify calculate global sched order was in fact run successfully before global scheduling? Also, verify your sched priority codes haven't been altered in the sched priority code maint form (crazier things have happened). Can you run your log file In a more verbose method? Id be willing to look at it closer..
>
> Rob Bucek
> Production Control Manager
> PH: (715) 284-5376 ext 311
> Mobile: (715)896-0590
> FAX: (715)284-4084
> [Description: cid:1.234354861@...]<http://www.dsmfg.com/>
> (Click the logo to view our site)<http://www.dsmfg.com/>
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of gamcb_1
> Sent: Thursday, March 15, 2012 10:46 AM
> To: vantage@yahoogroups.com
> Subject: [Vantage] Global Scheduling gone wonky - Vista 8.03-409c
>
>
>
> Global Scheduling has suddenly gone haywire. I have MRP, un-firmed jobs with Normal priority due in June being scheduled to start today, but firmed, released jobs that are needed to ship next week with High priority scheduled to start 3 weeks from now.
> We had a 10-day receive time on one customer for QC, but because of issues we started releasing jobs inside of 10 days. That was when I started getting the message "The job cannot be scheduled for its requested date due to system setting". I took the receive time off and I took the part number off each released job then put it back. It didn't solve the problem.
> I ran the Scheduler with log and have several repeats of the same "cannot be scheduled" message. I also got the following that I don't know what it means or if it is related:
> 15:54:30 Processing Jobs...
> 16:25:01 Process 102 not responding. Abandoned during process 'Done'
> 16:27:26 disconnect Mrp Process 101
> 16:27:45 disconnect Mrp Process 102
> 16:27:45 Sched process finished.
> How can I get my schedule back in line?
> Georgia McBroom
>
> Master Scheduler
>
> Skilcraft LLC
>
>
>
> [Non-text portions of this message have been removed]
>
Global Scheduling has suddenly gone haywire. I have MRP, un-firmed jobs with Normal priority due in June being scheduled to start today, but firmed, released jobs that are needed to ship next week with High priority scheduled to start 3 weeks from now.
We had a 10-day receive time on one customer for QC, but because of issues we started releasing jobs inside of 10 days. That was when I started getting the message "The job cannot be scheduled for its requested date due to system setting". I took the receive time off and I took the part number off each released job then put it back. It didn't solve the problem.
I ran the Scheduler with log and have several repeats of the same "cannot be scheduled" message. I also got the following that I don't know what it means or if it is related:
15:54:30 Processing Jobs...
16:25:01 Process 102 not responding. Abandoned during process 'Done'
16:27:26 disconnect Mrp Process 101
16:27:45 disconnect Mrp Process 102
16:27:45 Sched process finished.
How can I get my schedule back in line?
Georgia McBroom

Master Scheduler

Skilcraft LLC
How long has this persisted? Just the last run or several runs? Can you verify calculate global sched order was in fact run successfully before global scheduling? Also, verify your sched priority codes haven't been altered in the sched priority code maint form (crazier things have happened). Can you run your log file In a more verbose method? Id be willing to look at it closer..

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-0590
FAX: (715)284-4084
[Description: cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of gamcb_1
Sent: Thursday, March 15, 2012 10:46 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Global Scheduling gone wonky - Vista 8.03-409c



Global Scheduling has suddenly gone haywire. I have MRP, un-firmed jobs with Normal priority due in June being scheduled to start today, but firmed, released jobs that are needed to ship next week with High priority scheduled to start 3 weeks from now.
We had a 10-day receive time on one customer for QC, but because of issues we started releasing jobs inside of 10 days. That was when I started getting the message "The job cannot be scheduled for its requested date due to system setting". I took the receive time off and I took the part number off each released job then put it back. It didn't solve the problem.
I ran the Scheduler with log and have several repeats of the same "cannot be scheduled" message. I also got the following that I don't know what it means or if it is related:
15:54:30 Processing Jobs...
16:25:01 Process 102 not responding. Abandoned during process 'Done'
16:27:26 disconnect Mrp Process 101
16:27:45 disconnect Mrp Process 102
16:27:45 Sched process finished.
How can I get my schedule back in line?
Georgia McBroom