Hi All,
E9.05.702A
I have an odd requirement, at least odd to me.
I’m working with someone who has jobs with many subassemblies that also have many subassemblies.
They have a scenario where they want a particular subassembly to schedule a start date way before the it’s needed, as define by the schedule of the rest of the job.
For example, the job schedule dictates that this particular subassembly isn’t needed until May and it only has 100 machine hours to complete but they want this subassembly to be schedule to start in March so that it is completed and is sitting on the shelf before it’s needed in May.
The need for this unusual scheduling need is related to machine capacity availability.
Is there some type settings that I can use to force the schedule to make the start date sooner than needed?
Joe Rojas
Epicor Application Manager
Nordson MEDICAL
261 Cedar Hill Street
Marlborough, MA 01752 USA
+1.508.597.1392 Phone
+1.774.826.9245 Mobile
joseph.rojas@nordsonmedical.commailto:joseph.rojas@nordsonmedical.com
nordsonmedical.com
Quality Works Here