My department has just started using generate POs. New PO suggestions and Change PO suggestions are creating suggestions for past dates. IE 2017 for a few new PO suggestions. Anyone have any clue why this would happen?
We’re also trying to figure out how to turn off change orders so EPICOR just kicks out new PO suggestions.
Yes, we are also running MRP. The parameters for the nightly regenerative are:
Cutoff Date: 1st of month + 4 months, dynamic
Then it’s only against purchased items. No other settings have been changed.
You don’t need to run both. If your part is checked for Process MRP and Generate Suggestions MRP will run the suggestions. Do you have Allow Historical Dates turned off?
Demand for raw materials is created by MRP (and some manual) job creation. The idea is to automate as much of the PO creation as we can. MRP is currently used only in semi-finished goods, which is a bit like a postponement program.