Finished Goods Store in Vantage ERP

If your using shop floor data collection you have "Current, Available and
Expected" tabs which show what items are "Available" for the operator to
work on next and are in date order.

Plan "B" would be your priority dispatch report which will show the same
type information as above. This can be used by a shop floor person to direct
what is done next or give to the operators of the equipment depending on the
mentality of your shop.

Plan "C" would be to create a global alter or dash board for someone to
react to when a setup or production run is complete.

Plan "D" have your operators walk around and pick the next job them self
hopefully using some type of intelligence looking at the scheduled dates on
travelers.

As for vantage if your way off on setup an run times or are very
inconsistent and want a quick realignment try "Load Leveling". Every couple
of jobs to pull in or push out the schedule.

Hope this helps.


Patrick Winter

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
bakerprovan
Sent: Wednesday, February 01, 2006 8:39 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Finished Goods Store in Vantage ERP

Hello! everyone

does anyone know how you can put some sort of mechanism on controlling the
scheduling jobs in Vantage 6.1, because for some situations after you have
set up jobs for a particular estimated time-frame, jobs arent always use up
the planned times. As for some job operations are finished ahead of time
and/or overtime.

How can I better manage this in Vantage 6.1? As when a job has finished with
a work centre at a particular time would like to start up the next job on
the same work centre to better manage the work centre and resources.

Any suggestions would be gladly appreciated. Thanks





Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
Yahoo! Groups Links
Hello! everyone

does anyone know how you can put some sort of mechanism on controlling
the scheduling jobs in Vantage 6.1, because for some situations after
you have set up jobs for a particular estimated time-frame, jobs arent
always use up the planned times. As for some job operations are
finished ahead of time and/or overtime.

How can I better manage this in Vantage 6.1? As when a job has
finished with a work centre at a particular time would like to start
up the next job on the same work centre to better manage the work
centre and resources.

Any suggestions would be gladly appreciated. Thanks
Take a look at the Priority Dispatch Report in Job Management. This report can print by workcenter and will show all jobs in the queue for that workcenter. It even categorizes them based on current, available and expected work (see online help Report Notes for this report for a detailed explanation of the categories).

I've been in many Vantage shops that will print this report by workcenter and will have it posted at the workcenters. If a job is completed early the operators can look at the listing to see what job should next be worked on.

Hope this helps.

Mike



-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]On Behalf Of bakerprovan
Sent: Wednesday, February 01, 2006 6:39 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Finished Goods Store in Vantage ERP


Hello! everyone

does anyone know how you can put some sort of mechanism on controlling
the scheduling jobs in Vantage 6.1, because for some situations after
you have set up jobs for a particular estimated time-frame, jobs arent
always use up the planned times. As for some job operations are
finished ahead of time and/or overtime.

How can I better manage this in Vantage 6.1? As when a job has
finished with a work centre at a particular time would like to start
up the next job on the same work centre to better manage the work
centre and resources.

Any suggestions would be gladly appreciated. Thanks





Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and Crystal Reports and other 'goodies', please goto: http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto: http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto: http://groups.yahoo.com/group/vantage/links




SPONSORED LINKS
Manufacturing <http://groups.yahoo.com/gads?t=ms&k=Manufacturing+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=OG5F3819UOUOg63i0bu6kA> software Membership <http://groups.yahoo.com/gads?t=ms&k=Membership+database+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=N5BGdur84p-jyuOomcQdbQ> database software Database <http://groups.yahoo.com/gads?t=ms&k=Database+mortgage+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=8rvcSQnCqJhTCZu-0Si39A> mortgage software
Pda <http://groups.yahoo.com/gads?t=ms&k=Pda+database+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=u3KQrTRPAQfsWIT39aHDkg> database software Database <http://groups.yahoo.com/gads?t=ms&k=Database+management+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=R3CF3ODPY4gwjDZjykQYvw> management software Database <http://groups.yahoo.com/gads?t=ms&k=Database+marketing+software&w1=Manufacturing+software&w2=Membership+database+software&w3=Database+mortgage+software&w4=Pda+database+software&w5=Database+management+software&w6=Database+marketing+software&c=6&s=188&.sig=lmBkRUiBtvHI1u5dkymDcw> marketing software

_____

YAHOO! GROUPS LINKS



* Visit your group " vantage <http://groups.yahoo.com/group/vantage> " on the web.


* To unsubscribe from this group, send an email to:
vantage-unsubscribe@yahoogroups.com <mailto:vantage-unsubscribe@yahoogroups.com?subject=Unsubscribe>


* Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service <http://docs.yahoo.com/info/terms/> .


_____




[Non-text portions of this message have been removed]