Yeah, thats what I do now. We have a scheduler who just wants to add one resource and not have to maintain separate resources
________________________________
From: Miguel Santillan <msantillan@...>
To: "vantage@yahoogroups.com" <vantage@yahoogroups.com>
Sent: Thursday, September 20, 2012 4:25 PM
Subject: RE: [Vantage] E9 - Resource Group - Number of Resources
Â
13 emp with 24 work hours?
You can create one resource, export to excel and then use excel to copy the cells and make res1, res2, res3 and then PASTE UPDATE to the Grid view
Miguel A. Santillan
Compass Components, Inc.
From: mailto:vantage%40yahoogroups.com [mailto:mailto:vantage%40yahoogroups.com] On Behalf Of Mark Wagner
Sent: Thursday, September 20, 2012 11:47 AM
To: Vantage User Group
Subject: [Vantage] E9 - Resource Group - Number of Resources
I think i know the answer to this already but had to ask in case I am missing something. If we have an assembly resource group of 40 employees, other than creating 40 individual resources to calculate my capacity, is there any other way to indicate we have 40 employees x 8 hours per day as available capacity?
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
________________________________
From: Miguel Santillan <msantillan@...>
To: "vantage@yahoogroups.com" <vantage@yahoogroups.com>
Sent: Thursday, September 20, 2012 4:25 PM
Subject: RE: [Vantage] E9 - Resource Group - Number of Resources
Â
13 emp with 24 work hours?
You can create one resource, export to excel and then use excel to copy the cells and make res1, res2, res3 and then PASTE UPDATE to the Grid view
Miguel A. Santillan
Compass Components, Inc.
From: mailto:vantage%40yahoogroups.com [mailto:mailto:vantage%40yahoogroups.com] On Behalf Of Mark Wagner
Sent: Thursday, September 20, 2012 11:47 AM
To: Vantage User Group
Subject: [Vantage] E9 - Resource Group - Number of Resources
I think i know the answer to this already but had to ask in case I am missing something. If we have an assembly resource group of 40 employees, other than creating 40 individual resources to calculate my capacity, is there any other way to indicate we have 40 employees x 8 hours per day as available capacity?
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]