We ended up creating a nonconformance for the job material based on other feedback in the group.
Thanks for everyone’s input.
JOE ROJAS
Epicor Applications Manager
VENTION MEDICAL
DIRECT: 508.481.6233 | MOBILE: 774.826.9245
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Thursday, May 05, 2016 5:12 PM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] E9: Moving Job Material to Inspection
Can you unreceive the parts (delete line on receipt)? Mark the PO line as Inspection required – then process receive them again?
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]
Sent: Thursday, May 05, 2016 2:01 PM
To: vantage@yahoogroups.com
Subject: [Vantage] E9: Moving Job Material to Inspection
Hi All,
It’s been a while since I’ve worked with the QA module.
A buyer forgot to check off Inspection Required on a PUR-MTL po line. As a result the material went straight to the job. The parts are physically sitting in the inspection department but they can’t see if in Inspection Processing for them to process.
How do I move the material from the job to Inspection so that they can complete the inspection process?
JOE ROJAS
Epicor Applications Manager
VENTION MEDICAL
DIRECT: 508.481.6233 | MOBILE: 774.826.924
This communication may contain information that is confidential, proprietary or exempt from disclosure, and is intended only for the use of the individual and/or entity it is addressed to. If you are not the intended recipient, please note that any other dissemination, distribution, use or copying of this communication is strictly prohibited. If you have received this message in error, please notify the sender immediately by telephone or by return e-mail, and delete this information from your computer.
[Non-text portions of this message have been removed]