Hi All,
I have 60 or so Projects I want to DMT into Epicor. I’m having trouble finding the Budget Material Cost field in DMT.
Is there a specific field I’m missing to use?
Hi All,
I have 60 or so Projects I want to DMT into Epicor. I’m having trouble finding the Budget Material Cost field in DMT.
Is there a specific field I’m missing to use?
If you are not using any WBS Phases, then the Project Combined DMT upload template adds the ProjectCst fields you’re looking for.
If you ARE using WBS Phases, then each Phase can have its own budget in the ProjPhase table.
I’ll try that, I looked at the Project Combined and saw a whole lot of required fields, which turned me away from it.