Confused with the revision selection logic of a Unfirmed job after a MRP run.If i am not wrong,the latest approved revision is selected while firm the job,if the job is for “Make to Stock” and the revision selected in Sales order entry for “Make to Order” case.
Here is the case where a part entered with revision “C” (approved on 2014) in Sales order, Ticked on “Make Direct”. After running the MRP for that part, An unfirmed job order is created with Revision C1,approved on year 2015.
Now i am confused,why did it happened ?
Any Help will be greatly appreciated.
1.Sales order(Line): C revision selected (approved on 2014)
2.Sales order (Release): Make Direct
3.Unfirmed job created with C1 revision (approved on 2015):