> What I am getting is our Finish Parts are picking up the LAST COST forIf you want to use Last Cost for your Purchased Items only then I
> labor and burden too.
>
think that you need to perform a two-step update process: first,
create a Cost Group and then request Last Cost as your Costing Method
when you "Get Cost Details" for Purchased Parts. Do not roll this
group up, just post it. Next, create another cost group, Get Details
for all your parts using the Standard Cost Method and roll this group
up as you normally would.
I just saw this demo'd at Perspectives in October in the Hall of
Solutions so I am guessing that the Vantage software level was 8.03.405a.
By all means, check it out in a test environment.
Peter Dunbar
Halm Industries Co., Inc.