BOM Cost report

Thanks!! Very helpful!!

________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Scott Litzau
Sent: Tuesday, November 11, 2008 10:05 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] BOM Cost report


If there is a Material, that is a manufactured part in the Method, then it
will show that as Material Cost in the report.

Now depending how the method is set up and if that manufactured part is not
marked with Pull or View As Assembly then it will only show as a material in
the report. But if either is marked it will breakdown those costs showing
the parts for that sub-assembly.

We are not big fans of the canned report but have learned to live with it.
It took us a little bit to understand how they were presenting the costs.

Scott Litzau, MCP
Olympus Flag & Banner
Information Systems Manager
scott.litzau@...<mailto:scott.litzau%40olympus-flag.com>
P: 414-365-9732
F: 414-355-1931

-----Original Message-----
From: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com> [mailto:vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>] On Behalf Of
Jasper Recto
Sent: Monday, November 10, 2008 3:19 PM
To: Vantage Groups (vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>)
Subject: [Vantage] BOM Cost report

When you run an Indented BOM Cost report, it breaks out the cost in to the 5
components.

For just the Material cost total, is that just the total of all Purchased
parts or is there something more to it?

Thanks,

[Non-text portions of this message have been removed]

------------------------------------

Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.<http://groups.yahoo.com/group/vantage/files/>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links



[Non-text portions of this message have been removed]
When you run an Indented BOM Cost report, it breaks out the cost in to the 5 components.

For just the Material cost total, is that just the total of all Purchased parts or is there something more to it?

Thanks,



[Non-text portions of this message have been removed]
If there is a Material, that is a manufactured part in the Method, then it
will show that as Material Cost in the report.

Now depending how the method is set up and if that manufactured part is not
marked with Pull or View As Assembly then it will only show as a material in
the report. But if either is marked it will breakdown those costs showing
the parts for that sub-assembly.

We are not big fans of the canned report but have learned to live with it.
It took us a little bit to understand how they were presenting the costs.

Scott Litzau, MCP
Olympus Flag & Banner
Information Systems Manager
scott.litzau@...
P: 414-365-9732
F: 414-355-1931


-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Jasper Recto
Sent: Monday, November 10, 2008 3:19 PM
To: Vantage Groups (vantage@yahoogroups.com)
Subject: [Vantage] BOM Cost report

When you run an Indented BOM Cost report, it breaks out the cost in to the 5
components.

For just the Material cost total, is that just the total of all Purchased
parts or is there something more to it?

Thanks,



[Non-text portions of this message have been removed]


------------------------------------

Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links