Hi,
Without a landed cost module, is there away to apply charges onto a PO receipt so that it can reflect on the Part Cost?
Thank You in Advance
Not Financial Consultant
Hi,
Without a landed cost module, is there away to apply charges onto a PO receipt so that it can reflect on the Part Cost?
Thank You in Advance
Not Financial Consultant
Material burden rate on the part. It is however set as percent of cost.
Are you referring to the Cost Adjustments option? If so, that is not what I am looking for as our costing is AVG type and we would like the cost to be reflect dynamically
Burden is set on the part. Part entry bottom section of the main part page. It’s not dynamic though. There is a licensed feature called landed cost you can buy. We don’t have that
We purchased the Landed Cost module for this exact reason. The part level material burden % didn’t cut it as our freight charges are not part specific and we did not want a watered down generic rate set across all parts.