The easiest way we have found to handle advance billings is to
set up a payment term that has 3 payments on it. We then do an
"Unreceived Billing Line" for 90K and "attach" it to the PO through
"Add line".
Then in the invoice header, update the payment dates to the
actual due dates. This way when we pull up the invoice for payment,
only the payment amount comes up and the balance is held in the
future
column.
When the material is received, receive it normally then go into
the "Invoice/Receipt Match" utility and match the invoice with the
receipt. This way the costs hit the job properly and it doesn't
require an adjustment.
Best regards,
Carol Silvey
Wisdom Industries, Ltd.
set up a payment term that has 3 payments on it. We then do an
"Unreceived Billing Line" for 90K and "attach" it to the PO through
"Add line".
Then in the invoice header, update the payment dates to the
actual due dates. This way when we pull up the invoice for payment,
only the payment amount comes up and the balance is held in the
future
column.
When the material is received, receive it normally then go into
the "Invoice/Receipt Match" utility and match the invoice with the
receipt. This way the costs hit the job properly and it doesn't
require an adjustment.
Best regards,
Carol Silvey
Wisdom Industries, Ltd.