Hi Lee,
I am in the process of trying to implement eScheduling now. The first thing
we found, was that we have a lot of cleaning up to do in Vantage. Production
has been real lax in making sure that operations were completed properly, in
the system, and we also found many orders that have been waiting (in some
cases years) for Proof approvals to come back. We have not done a good job
of keeping the information in Vantage Clean and current. We also found that
there are many operation standards that need to be addressed, in order for
eSchedule to be of any use. In our case, there is much preliminary work to
be done. I've taken the eScheduling class and understand the theory behind
the program. It's quite impressive. Whether we can make it work effectively
or not, has yet to be determined. If resources will allow, I would highly
reccommend the services of Kevin Rosell from Epicor. Kevin is well versed in
eScheduling, as well as having much knowledge of Vantage and manufacturing
processes. I understand that he will only be doing customer sites, through
this summer.
Regards,
Les Tingley
MIS
Decorated Products
I am in the process of trying to implement eScheduling now. The first thing
we found, was that we have a lot of cleaning up to do in Vantage. Production
has been real lax in making sure that operations were completed properly, in
the system, and we also found many orders that have been waiting (in some
cases years) for Proof approvals to come back. We have not done a good job
of keeping the information in Vantage Clean and current. We also found that
there are many operation standards that need to be addressed, in order for
eSchedule to be of any use. In our case, there is much preliminary work to
be done. I've taken the eScheduling class and understand the theory behind
the program. It's quite impressive. Whether we can make it work effectively
or not, has yet to be determined. If resources will allow, I would highly
reccommend the services of Kevin Rosell from Epicor. Kevin is well versed in
eScheduling, as well as having much knowledge of Vantage and manufacturing
processes. I understand that he will only be doing customer sites, through
this summer.
Regards,
Les Tingley
MIS
Decorated Products
> -----Original Message-----
> From: Lee Ingalls [SMTP:eli3@...]
> Sent: Friday, April 26, 2002 9:00 AM
> To: Vantage user forum
> Subject: [Vantage] Advanced Planning and Scheduling
>
>
> Good Morning Colleagues,
>
> Looking for feedback from those of you who have experience with
> eScheduling
> (Advanced Planning and Scheduling)... the add-on module to Visual
> Scheduling.
>
> Thanks in advance, Lee
>
> E. Lee Ingalls III
> Information Technologies
> Commercial Tool & Die, Inc.
> (p) 616.785.8100
> (f) 616.785.8210
>
> [Non-text portions of this message have been removed]
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
> have already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder and
> Crystal Reports and other 'goodies', please goto:
> http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
> http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
> http://groups.yahoo.com/group/vantage/links
>
> Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
>