Adjusting scheduling factors on JobEntry

Is there a way to adjust the production factor on an operation within Job Entry in the same way that you can apply the production factor to a resource through a capability?

Trying to compress the scheduled duration of an operation without affecting the estimated hours of the op.
In reality we’re going to have additional team members working on the task to achieve the shorter turnaround but don’t want to change the actual planned requirement.