Stuart
In Vantage 8.00 and onwards a function was added called 'remove from
Schedule' which does what I think you are asking
The work around in Vantage 6.1, is to schedule the job for Christmas Day
2020 (or another unreasonable date)
Then make sure a cut off date prior to the unreasonable date is set when
you run MRP or Suggestions.
This will then exclude the jobs requirements. Sometimes a checkbox
labelled 'On Hold' is also used to identify the job for searching
purposes
Gary
Dot Net IT Limited, Reg No 4412519
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Stuart Noble
Sent: 14 December 2007 21:17
To: vantage@yahoogroups.com
Subject: [Vantage] 6.1 MRP Scheduling Issue
Hi All,
We have the following issue. We firm an MRP job and thus schedule the
job as a basic practice from MRP, and then I as production manager
review jobs to ensure nothing is wrong.
One job with multiple sub jobs I decide I am not happy with, and need to
investigate matters further. But nothing I do will release all the parts
from PO suggestions, so invariably Purchasing have or will be ordering
the material already by the time I find out.
Does anyone have any solutions to this problem, I almost need the option
of unticking the firm box on the job?
Any input or feedback would be thankfully received!
Stuart
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
In Vantage 8.00 and onwards a function was added called 'remove from
Schedule' which does what I think you are asking
The work around in Vantage 6.1, is to schedule the job for Christmas Day
2020 (or another unreasonable date)
Then make sure a cut off date prior to the unreasonable date is set when
you run MRP or Suggestions.
This will then exclude the jobs requirements. Sometimes a checkbox
labelled 'On Hold' is also used to identify the job for searching
purposes
Gary
Dot Net IT Limited, Reg No 4412519
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Stuart Noble
Sent: 14 December 2007 21:17
To: vantage@yahoogroups.com
Subject: [Vantage] 6.1 MRP Scheduling Issue
Hi All,
We have the following issue. We firm an MRP job and thus schedule the
job as a basic practice from MRP, and then I as production manager
review jobs to ensure nothing is wrong.
One job with multiple sub jobs I decide I am not happy with, and need to
investigate matters further. But nothing I do will release all the parts
from PO suggestions, so invariably Purchasing have or will be ordering
the material already by the time I find out.
Does anyone have any solutions to this problem, I almost need the option
of unticking the firm box on the job?
Any input or feedback would be thankfully received!
Stuart
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]