407 ETA Blank Title 72026

On any given day (we run global nightly) about 30% of our finite resource scheduled jobs have OPs scheduled out of sequence (completely disrespecting the Finish-to-Start relationship of our OPs).

I'm not talking a 'little' off: Example: Job 123 has OP5 scheduled to start in mid March. OP10 will be scheduled to start IMMEDIATELY (today).

If materials are associated with these out-of sequence scheduled OPs it plays hell with material planning.

406 didn't fix it (and broke other things so we chose not to upgrade). 407 release notes hint that the problem is acknowledged. We'll be testing that this month.

Support has been useless. After MONTHs of back and forth (and even with a copy of our db) they have yet to acknowledge the problem. My last contact with them (2 weeks ago) I had then dump the JobHed, JobOper & JobOpDtl tables to csv and I pulled them into excel and SHOWED them the massively mischeduled OPs. After getting a "I'll call you tomorrow" response, I'm still awaiting the call back.

On Monday I start the escalation process. If they don't have support ON-SITE within a week (we are 15 minutes from their Parsippany NJ hub), I'll be recommending we dump support for the current year and file suit to recover last year's fees.

This product is not giving us a competitive edge over our competition. It is an OBSTACLE.

The 404 bugs (which we alerted them to and they fixed in 405) were with the Calculate Global Scheduling Order application. They were using the wrong date in the calculation (due date instead of required date) and also weren't using the scheduling code multiplier.

This COULD be an OK product if they didn't treat their customers like an enemy to be sucked dry via support fees (with no support in return for those fees).

I'll be surprised if they survive this recession.

Rob

--- On Fri, 1/2/09, melissa hietala <kevmel822@...> wrote:
From: melissa hietala <kevmel822@...>
Subject: Re: [Vantage] Re: 407 ETA
To: vantage@yahoogroups.com
Date: Friday, January 2, 2009, 11:19 AM











What is the global scheduling bug you are referring to here? We have just started using at and have a few issues.

Thanks

 Melissa Hietala

UMC, Inc.

melissah@ultramc. com



____________ _________ _________ __

From: Robert Brown <robertb_versa@ yahoo.com>

To: vantage@yahoogroups .com

Sent: Thursday, December 18, 2008 7:20:15 AM

Subject: Re: [Vantage] Re: 407 ETA



Vic,



Clive is right (in our experience). 404 was an abomination (re bugs). 405(a) is much better (although still one HUGE bug with global scheduling - that 406 doesn't fix as we've tested).



I'd consider 405. If you're customized, the only area we found it broke customizations (404 to 405) was with PO Entry. Most of our customization in PO Entry to were self-fix bugs and they actually fixed many of the bugs (and cclearly made some major under the hood changes) so our 404 PO Entry customizations broke.



Other than that, the only thing close to being an OK (quality) release I've seen out of Epicor.



We don't feel compelled to blindly upgrade either. (More trouble than it's worth with Epicor's horrific release quality track record.)



I'm with you... I'll wait for v10 before seriously considering v9 & let others more daring do Epicor's QC for them. ....They should pay US! :)



We're in business to serve our customers & try to eke out a profit - Not just blindly play with the latest/greatest claimed Epicor offering & devote hundreds of hours to doing there QC for them.



Rob



--- On Thu, 12/18/08, clive.1972 <clive.1972@ yahoo. com> wrote:

From: clive.1972 <clive.1972@ yahoo. com>

Subject: [Vantage] Re: 407 ETA

To: vantage@yahoogroups .com

Date: Thursday, December 18, 2008, 3:21 AM



Vic,



I can remember at least three big bugs that were fixed in 405, you may



want to check the change list for 405 to see what bugs you're still



running with.



There's one fixed that can effect costs on materials issued to jobs and



another that sorts out a problem with change logs.



--- In vantage@yahoogroups .com, "Vic Drecchio" <vic.drecchio@ ...> wrote:



>



> I'm on 404B and staying. Why? It works.



>



> I've NEVER been a big fan of upgrading "just because" someone decides



to release a service pack.



>



> To this day I disable Windows Update on everything I own.



>



> "If it ain't broke, don't fix it."



>



> I learn the nuances and work-arounds on my version and stick with



it. Because every time an "upgrade" or "patch" is applied, 10 other



unknown new problems are revealed.



>



> I'm with Jonathan.... .. but I'll wait for Vantage 10. :-)



>



[Non-text portions of this message have been removed]
Does any one know what the ETA is for 407 cuz we have been told that a
problem we are having is going to be fixed on that SP and they are not doing
a one off for the problem.



~Charlie









[Non-text portions of this message have been removed]
Hi Charlie,

We too are waiting for a fix in 407. I have been told they are already starting work on 408, so 407 must be anytime soon.

I can't understand how Vantage has been going as a product for ages and they are still just getting round to fixing some of the faults. Now they have brought 9 out which is likely to be full of faults just the same.

I will keep you updated if/when I find out about the release date.

Cheers,


CHRIS




________________________________
From: Charlie Wilson <foamdesigncsw@...>
To: vantage@yahoogroups.com
Sent: Monday, December 15, 2008 4:10:20 PM
Subject: [Vantage] 407 ETA


Does any one know what the ETA is for 407 cuz we have been told that a
problem we are having is going to be fixed on that SP and they are not doing
a one off for the problem.

~Charlie

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]
I've been told that 407 was to be out this somewhen week, fingers
crossed, with 408 for somewhen in February 2009.

--- In vantage@yahoogroups.com, "Charlie Wilson" <foamdesigncsw@...>
wrote:
>
> Does any one know what the ETA is for 407 cuz we have been told
that a
> problem we are having is going to be fixed on that SP and they are
not doing
> a one off for the problem.
>
>
>
> ~Charlie
>
>
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
OH BOY!! MORE BUGS TO PLAY WITH!! Oh wait, they're not bugs they're FEATURES!
Â
Every release brings that many more problems. I'll wait for 9.x.
Â
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
jlang@...


--- On Wed, 12/17/08, clive.1972 <clive.1972@...> wrote:

From: clive.1972 <clive.1972@...>
Subject: [Vantage] Re: 407 ETA
To: vantage@yahoogroups.com
Date: Wednesday, December 17, 2008, 2:29 AM






I've been told that 407 was to be out this somewhen week, fingers
crossed, with 408 for somewhen in February 2009.

--- In vantage@yahoogroups .com, "Charlie Wilson" <foamdesigncsw@ ...>
wrote:
>
> Does any one know what the ETA is for 407 cuz we have been told
that a
> problem we are having is going to be fixed on that SP and they are
not doing
> a one off for the problem.
>
>
>
> ~Charlie
>
>
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>


















[Non-text portions of this message have been removed]
I'm on 404B and staying. Why? It works.

I've NEVER been a big fan of upgrading "just because" someone decides to release a service pack.

To this day I disable Windows Update on everything I own.

"If it ain't broke, don't fix it."

I learn the nuances and work-arounds on my version and stick with it. Because every time an "upgrade" or "patch" is applied, 10 other unknown new problems are revealed.

I'm with Jonathan...... but I'll wait for Vantage 10. :-)

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Jonathan Lang
Sent: Wednesday, December 17, 2008 9:18 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Re: 407 ETA

OH BOY!! MORE BUGS TO PLAY WITH!! Oh wait, they're not bugs they're FEATURES!
Â
Every release brings that many more problems. I'll wait for 9.x.
Â
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
jlang@...


--- On Wed, 12/17/08, clive.1972 <clive.1972@...> wrote:

From: clive.1972 <clive.1972@...>
Subject: [Vantage] Re: 407 ETA
To: vantage@yahoogroups.com
Date: Wednesday, December 17, 2008, 2:29 AM






I've been told that 407 was to be out this somewhen week, fingers
crossed, with 408 for somewhen in February 2009.

--- In vantage@yahoogroups .com, "Charlie Wilson" <foamdesigncsw@ ...>
wrote:
>
> Does any one know what the ETA is for 407 cuz we have been told
that a
> problem we are having is going to be fixed on that SP and they are
not doing
> a one off for the problem.
>
>
>
> ~Charlie
>
>
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>


















[Non-text portions of this message have been removed]


------------------------------------

Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and Crystal Reports and other 'goodies', please goto: http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto: http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto: http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links
>
> Every release brings that many more problems. I'll wait for 9.x.
>

Oh, Dude...

Mark "with open issues on 9" W.
Mark,
Â
Notice the 9."x". I'll wait for a later version of the kernel before upgrading. Everytime upgrades come out that fixes a problem I have, I cringe wondering what chaos the patch will unleash on my DB.
Â
I did upgrade to 406A because it fixed a HUGE problem with Job Closing. After the upgrade was finished I noticed that all of the Primary Bins had been erased from many parts, not all. When I ran a report to see how many parts had no Primary Bin it counted 19,056 parts.
Â
There were many other "little" problems I had to fix, but you are left with a queezy feeling after the upgrade has been accomplished.
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
jlang@...


--- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@...> wrote:

From: Mark Wonsil <mark_wonsil@...>
Subject: RE: [Vantage] Re: 407 ETA
To: vantage@yahoogroups.com
Date: Wednesday, December 17, 2008, 9:53 AM






>
> Every release brings that many more problems. I'll wait for 9.x.
>

Oh, Dude...

Mark "with open issues on 9" W.


















[Non-text portions of this message have been removed]
Mark, what's your pragmatic sense on the quality of the 9.0 code you
got? I know that what went to RTM was not what you started with.



My sense is that 9.0 is something of a big service pack from 8.3,
which implies a thorough level of testing, but something less than a
turn-the-world-upside-down kind of activity. Based on feedback I've
heard here and elsewhere, Vantage SPs aren't as painless as one might
hope for but I'm hoping that its better than it could be.



We did a few customer references before our buy decision and the folks
we talked to were happy with the product quality, updates, and
functionality. The tone in this group is somewhat more mixed (which is
to be expected).



-bws



--

Brian W. Spolarich ~ Manager, Information Services ~ Advanced Photonix /
Picometrix

bspolarich@... ~ 734-864-5618 ~
www.advancedphotonix.com



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Mark Wonsil
Sent: Wednesday, December 17, 2008 10:54 AM
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Re: 407 ETA



>
> Every release brings that many more problems. I'll wait for 9.x.
>

Oh, Dude...

Mark "with open issues on 9" W.






[Non-text portions of this message have been removed]
> My sense is that 9.0 is something of a big service pack from 8.3,
> which implies a thorough level of testing, but something less than a
> turn-the-world-upside-down kind of activity. Based on feedback I've
> heard here and elsewhere, Vantage SPs aren't as painless as one might
> hope for but I'm hoping that its better than it could be.

It's a REALLY BIG service pack. Yes, the foundation tools for the UI, etc.
are the same but there are some serious under-the-hood changes that can/will
turn your world upside-down. The most notable is in the financials. Account
number segments are now user-defined. You're not restricted to
Div-Dept-Acct. You can have up to a ridiculously high account number length
(100+) and as many segments that you can fit in there. The whole posting to
the G/L is now table driven to allow to posting to multiple books for
different purposes. Unit of Measure capability is much different, including
conversion factors and different UOM fields on a part for stock, purchasing,
and selling. The physical inventory and cycle count is MUCH more structured
than before. The new BAQ designer (graphical) lets you use the same table
(alias) more than once. There's something that I haven't tested yet and
that's BPM forms. You can design a form (text input, radio, dropdown,
buttons) and gather information during an event like a dialog box. "Do you
want to continue?" or "Enter the heat lot number", etc. And then there's new
stuff like vendor/customer managed inventory.

A lot of these changes come from the other Epicor product lines. Since the
migration path is toward 9 for ALL Epicor companies, they need to make sure
that 9 has enough of the same capabilities to make folks migrate.

I would say it certainly deserves the moniker 9 instead of 8.1, that's for
sure. As for quality, ...well..., I'm having a bad quality day today but
Epicor has been quite responsive. Ask me again on January 5th at 5:00 PM.

;-)

Mark W.
Mark,

In the UK they still haven't got their physical media for 9 to send
to customers (which I've asked for) so I presume that you were a beta
tester ?.

Now that it's out you can spill the beans ;-)

Have you been involved at all with Microsoft Performance Point (I'm
interested in it's KPI's). Also have Epicor made any changes to the
licensing, e.g. to use the new reporting tools (Microsoft stuff) you
have to get licenses for them from Epicor, they don't come with it.

I've been through the help files and what you can get on-line but I
can't get a handle on whether or not any work has been put into the
standard out of the box reports, I presume there's still a lot of
Progress/text reports in there ?.

With the new BAQ designer, and its multiple table references, can you
refer back to a table allmost infinetely ?, e.g. create a BAQ that
you could use to output a full BOM ?.

Thanks.

--- In vantage@yahoogroups.com, "Mark Wonsil" <mark_wonsil@...> wrote:
>
> It's a REALLY BIG service pack. Yes, the foundation tools for the
UI, etc.
> are the same but there are some serious under-the-hood changes that
can/will
> turn your world upside-down. The most notable is in the financials.
Account
> number segments are now user-defined. You're not restricted to
> Div-Dept-Acct. You can have up to a ridiculously high account
number length
> (100+) and as many segments that you can fit in there. The whole
posting to
> the G/L is now table driven to allow to posting to multiple books
for
> different purposes. Unit of Measure capability is much different,
including
> conversion factors and different UOM fields on a part for stock,
purchasing,
> and selling. The physical inventory and cycle count is MUCH more
structured
> than before. The new BAQ designer (graphical) lets you use the same
table
> (alias) more than once. There's something that I haven't tested yet
and
> that's BPM forms. You can design a form (text input, radio,
dropdown,
> buttons) and gather information during an event like a dialog
box. "Do you
> want to continue?" or "Enter the heat lot number", etc. And then
there's new
> stuff like vendor/customer managed inventory.
>
> A lot of these changes come from the other Epicor product lines.
Since the
> migration path is toward 9 for ALL Epicor companies, they need to
make sure
> that 9 has enough of the same capabilities to make folks migrate.
>
> I would say it certainly deserves the moniker 9 instead of 8.1,
that's for
> sure. As for quality, ...well..., I'm having a bad quality day
today but
> Epicor has been quite responsive. Ask me again on January 5th at
5:00 PM.
>
> ;-)
>
> Mark W.
>
Vic,

I can remember at least three big bugs that were fixed in 405, you may
want to check the change list for 405 to see what bugs you're still
running with.

There's one fixed that can effect costs on materials issued to jobs and
another that sorts out a problem with change logs.

--- In vantage@yahoogroups.com, "Vic Drecchio" <vic.drecchio@...> wrote:
>
> I'm on 404B and staying. Why? It works.
>
> I've NEVER been a big fan of upgrading "just because" someone decides
to release a service pack.
>
> To this day I disable Windows Update on everything I own.
>
> "If it ain't broke, don't fix it."
>
> I learn the nuances and work-arounds on my version and stick with
it. Because every time an "upgrade" or "patch" is applied, 10 other
unknown new problems are revealed.
>
> I'm with Jonathan...... but I'll wait for Vantage 10. :-)
>
Vic,

I can remember at least three big bugs that were fixed in 405, you may
want to check the change list for 405 to see what bugs you're still
running with.

There's one fixed that can effect costs on materials issued to jobs and
another that sorts out a problem with change logs.

--- In vantage@yahoogroups.com, "Vic Drecchio" <vic.drecchio@...> wrote:
>
> I'm on 404B and staying. Why? It works.
>
> I've NEVER been a big fan of upgrading "just because" someone decides
to release a service pack.
>
> To this day I disable Windows Update on everything I own.
>
> "If it ain't broke, don't fix it."
>
> I learn the nuances and work-arounds on my version and stick with
it. Because every time an "upgrade" or "patch" is applied, 10 other
unknown new problems are revealed.
>
> I'm with Jonathan...... but I'll wait for Vantage 10. :-)
>
Vic,

Clive is right (in our experience). 404 was an abomination (re bugs). 405(a) is much better (although still one HUGE bug with global scheduling - that 406 doesn't fix as we've tested).

I'd consider 405. If you're customized, the only area we found it broke customizations (404 to 405) was with PO Entry. Most of our customization in PO Entry to were self-fix bugs and they actually fixed many of the bugs (and cclearly made some major under the hood changes) so our 404 PO Entry customizations broke.

Other than that, the only thing close to being an OK (quality) release I've seen out of Epicor.

We don't feel compelled to blindly upgrade either. (More trouble than it's worth with Epicor's horrific release quality track record.)

I'm with you... I'll wait for v10 before seriously considering v9 & let others more daring do Epicor's QC for them. ...They should pay US! :)

We're in business to serve our customers & try to eke out a profit - Not just blindly play with the latest/greatest claimed Epicor offering & devote hundreds of hours to doing there QC for them.

Rob

--- On Thu, 12/18/08, clive.1972 <clive.1972@...> wrote:
From: clive.1972 <clive.1972@...>
Subject: [Vantage] Re: 407 ETA
To: vantage@yahoogroups.com
Date: Thursday, December 18, 2008, 3:21 AM











Vic,



I can remember at least three big bugs that were fixed in 405, you may

want to check the change list for 405 to see what bugs you're still

running with.



There's one fixed that can effect costs on materials issued to jobs and

another that sorts out a problem with change logs.



--- In vantage@yahoogroups .com, "Vic Drecchio" <vic.drecchio@ ...> wrote:

>

> I'm on 404B and staying. Why? It works.

>

> I've NEVER been a big fan of upgrading "just because" someone decides

to release a service pack.

>

> To this day I disable Windows Update on everything I own.

>

> "If it ain't broke, don't fix it."

>

> I learn the nuances and work-arounds on my version and stick with

it. Because every time an "upgrade" or "patch" is applied, 10 other

unknown new problems are revealed.

>

> I'm with Jonathan.... .. but I'll wait for Vantage 10. :-)

>
> In the UK they still haven't got their physical media for 9 to send
> to customers (which I've asked for) so I presume that you were a beta
> tester ?.

Yes we are.

> Now that it's out you can spill the beans ;-)

I felt I've been spilling the beans quite well right along!

> Have you been involved at all with Microsoft Performance Point (I'm
> interested in it's KPI's). Also have Epicor made any changes to the
> licensing, e.g. to use the new reporting tools (Microsoft stuff) you
> have to get licenses for them from Epicor, they don't come with it.

The only experience I had is the KPI session at Perspectives. I'm assuming
that was the Performance Point demo. It was impressive. It looks like the
new BI model is having Cube Connect build the OLAP cubes and then letting
the users use whatever OLAP viewer they want. Since the cubes are in SQL,
it's natural to use Performance Point but I think you're not restricted.

> I've been through the help files and what you can get on-line but I
> can't get a handle on whether or not any work has been put into the
> standard out of the box reports, I presume there's still a lot of
> Progress/text reports in there ?.

There are still a few Progress reports but more have been moved to Crystal.

> With the new BAQ designer, and its multiple table references, can you
> refer back to a table allmost infinetely ?, e.g. create a BAQ that
> you could use to output a full BOM ?.

Ooooh, good question. I'll try, but right now we're under a time crunch.
I've been posting during conversion runs. I'll be doing conversion #6 next
week before the live conversion on New Years Eve. (Fingers crossed)

Mark W.
Jonathan,

When you had the problem with the wiping of the Primary Bins, how did you resolve it?

Has anybody else had this problem from upgrading to 406a?

We are only on 404 and Epicor are doing some customisation for us but we need to be on 407 - That'll be fun by the sounds of things!

Cheers,


CHRIS




________________________________
From: Jonathan Lang <lsbestinc@...>
To: vantage@yahoogroups.com
Sent: Wednesday, December 17, 2008 5:29:03 PM
Subject: RE: [Vantage] Re: 407 ETA


Mark,
Â
Notice the 9."x". I'll wait for a later version of the kernel before upgrading. Everytime upgrades come out that fixes a problem I have, I cringe wondering what chaos the patch will unleash on my DB.
Â
I did upgrade to 406A because it fixed a HUGE problem with Job Closing. After the upgrade was finished I noticed that all of the Primary Bins had been erased from many parts, not all. When I ran a report to see how many parts had no Primary Bin it counted 19,056 parts.
Â
There were many other "little" problems I had to fix, but you are left with a queezy feeling after the upgrade has been accomplished.
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
jlang@oilrite. com

--- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@ yahoo.com> wrote:

From: Mark Wonsil <mark_wonsil@ yahoo.com>
Subject: RE: [Vantage] Re: 407 ETA
To: vantage@yahoogroups .com
Date: Wednesday, December 17, 2008, 9:53 AM

>
> Every release brings that many more problems. I'll wait for 9.x.
>

Oh, Dude...

Mark "with open issues on 9" W.

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]
Hi,

Ive just been notified that .407 has been released (it was released on 20th December).

Thanks,


CHRIS




________________________________
From: Chris Thompson <chriselectrix@...>
To: vantage@yahoogroups.com
Sent: Thursday, December 18, 2008 3:43:15 PM
Subject: Re: [Vantage] Re: 407 ETA


Jonathan,

When you had the problem with the wiping of the Primary Bins, how did you resolve it?

Has anybody else had this problem from upgrading to 406a?

We are only on 404 and Epicor are doing some customisation for us but we need to be on 407 - That'll be fun by the sounds of things!

Cheers,

CHRIS

____________ _________ _________ __
From: Jonathan Lang <lsbestinc@yahoo. com>
To: vantage@yahoogroups .com
Sent: Wednesday, December 17, 2008 5:29:03 PM
Subject: RE: [Vantage] Re: 407 ETA

Mark,
Â
Notice the 9.."x". I'll wait for a later version of the kernel before upgrading. Everytime upgrades come out that fixes a problem I have, I cringe wondering what chaos the patch will unleash on my DB.
Â
I did upgrade to 406A because it fixed a HUGE problem with Job Closing. After the upgrade was finished I noticed that all of the Primary Bins had been erased from many parts, not all. When I ran a report to see how many parts had no Primary Bin it counted 19,056 parts.
Â
There were many other "little" problems I had to fix, but you are left with a queezy feeling after the upgrade has been accomplished.
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
jlang@oilrite. com

--- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@ yahoo.com> wrote:

From: Mark Wonsil <mark_wonsil@ yahoo.com>
Subject: RE: [Vantage] Re: 407 ETA
To: vantage@yahoogroups .com
Date: Wednesday, December 17, 2008, 9:53 AM

>
> Every release brings that many more problems. I'll wait for 9.x.
>

Oh, Dude...

Mark "with open issues on 9" W.

[Non-text portions of this message have been removed]

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]
No big bug fixes for our business there, I'll hang fire until 408 in
February 2009 I think...

--- In vantage@yahoogroups.com, Chris Thompson <chriselectrix@...>
wrote:
>
> Hi,
>
> Ive just been notified that .407 has been released (it was released
on 20th December).
>
> Thanks,
>
>
> CHRIS
>
>
>
>
> ________________________________
> From: Chris Thompson <chriselectrix@...>
> To: vantage@yahoogroups.com
> Sent: Thursday, December 18, 2008 3:43:15 PM
> Subject: Re: [Vantage] Re: 407 ETA
>
>
> Jonathan,
>
> When you had the problem with the wiping of the Primary Bins, how
did you resolve it?
>
> Has anybody else had this problem from upgrading to 406a?
>
> We are only on 404 and Epicor are doing some customisation for us
but we need to be on 407 - That'll be fun by the sounds of things!
>
> Cheers,
>
> CHRIS
>
> ____________ _________ _________ __
> From: Jonathan Lang <lsbestinc@yahoo. com>
> To: vantage@yahoogroups .com
> Sent: Wednesday, December 17, 2008 5:29:03 PM
> Subject: RE: [Vantage] Re: 407 ETA
>
> Mark,
> Â
> Notice the 9.."x". I'll wait for a later version of the kernel
before upgrading. Everytime upgrades come out that fixes a problem I
have, I cringe wondering what chaos the patch will unleash on my DB.
> Â
> I did upgrade to 406A because it fixed a HUGE problem with Job
Closing. After the upgrade was finished I noticed that all of the
Primary Bins had been erased from many parts, not all. When I ran a
report to see how many parts had no Primary Bin it counted 19,056
parts.
> Â
> There were many other "little" problems I had to fix, but you are
left with a queezy feeling after the upgrade has been accomplished.
> Jonathan LangÂ
> Oil Rite Corporation
> Sr. Network Administrator
> Ph: (920) 682-6173 Ext: 126
> Fax: (920) 682-7699
> jlang@oilrite. com
>
> --- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@ yahoo.com> wrote:
>
> From: Mark Wonsil <mark_wonsil@ yahoo.com>
> Subject: RE: [Vantage] Re: 407 ETA
> To: vantage@yahoogroups .com
> Date: Wednesday, December 17, 2008, 9:53 AM
>
> >
> > Every release brings that many more problems. I'll wait for 9.x.
> >
>
> Oh, Dude...
>
> Mark "with open issues on 9" W.
>
> [Non-text portions of this message have been removed]
>
> [Non-text portions of this message have been removed]
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
Looks like a big fix for us. According to the patch guide, they fixed the problem in the configurator where it ignores the keep when rules when creating a part. I'll let you know if they really did next week when I get a chance to test it.




________________________________
From: clive.1972 <clive.1972@...>
To: vantage@yahoogroups.com
Sent: Monday, December 22, 2008 10:55:30 AM
Subject: [Vantage] Re: 407 ETA


No big bug fixes for our business there, I'll hang fire until 408 in
February 2009 I think...

--- In vantage@yahoogroups .com, Chris Thompson <chriselectrix@ ...>
wrote:
>
> Hi,
>
> Ive just been notified that .407 has been released (it was released
on 20th December).
>
> Thanks,
>
>
> CHRIS
>
>
>
>
> ____________ _________ _________ __
> From: Chris Thompson <chriselectrix@ ...>
> To: vantage@yahoogroups .com
> Sent: Thursday, December 18, 2008 3:43:15 PM
> Subject: Re: [Vantage] Re: 407 ETA
>
>
> Jonathan,
>
> When you had the problem with the wiping of the Primary Bins, how
did you resolve it?
>
> Has anybody else had this problem from upgrading to 406a?
>
> We are only on 404 and Epicor are doing some customisation for us
but we need to be on 407 - That'll be fun by the sounds of things!
>
> Cheers,
>
> CHRIS
>
> ____________ _________ _________ __
> From: Jonathan Lang <lsbestinc@yahoo. com>
> To: vantage@yahoogroups .com
> Sent: Wednesday, December 17, 2008 5:29:03 PM
> Subject: RE: [Vantage] Re: 407 ETA
>
> Mark,
> Â
> Notice the 9.."x". I'll wait for a later version of the kernel
before upgrading. Everytime upgrades come out that fixes a problem I
have, I cringe wondering what chaos the patch will unleash on my DB.
> Â
> I did upgrade to 406A because it fixed a HUGE problem with Job
Closing. After the upgrade was finished I noticed that all of the
Primary Bins had been erased from many parts, not all. When I ran a
report to see how many parts had no Primary Bin it counted 19,056
parts.
> Â
> There were many other "little" problems I had to fix, but you are
left with a queezy feeling after the upgrade has been accomplished.
> Jonathan LangÂ
> Oil Rite Corporation
> Sr. Network Administrator
> Ph: (920) 682-6173 Ext: 126
> Fax: (920) 682-7699
> jlang@oilrite. com
>
> --- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@ yahoo.com> wrote:
>
> From: Mark Wonsil <mark_wonsil@ yahoo.com>
> Subject: RE: [Vantage] Re: 407 ETA
> To: vantage@yahoogroups .com
> Date: Wednesday, December 17, 2008, 9:53 AM
>
> >
> > Every release brings that many more problems. I'll wait for 9.x.
> >
>
> Oh, Dude...
>
> Mark "with open issues on 9" W.
>
> [Non-text portions of this message have been removed]
>
> [Non-text portions of this message have been removed]
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>






[Non-text portions of this message have been removed]
Partial shipment issue seems to be fixed that is what I am after.

________________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Steven Gotschall
Sent: Monday, December 22, 2008 11:53 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] Re: 407 ETA

Looks like a big fix for us. According to the patch guide, they fixed the
problem in the configurator where it ignores the keep when rules when
creating a part. I'll let you know if they really did next week when I get
a chance to test it.

________________________________
From: clive.1972 <clive.1972@...>
To: vantage@yahoogroups.com
Sent: Monday, December 22, 2008 10:55:30 AM
Subject: [Vantage] Re: 407 ETA

No big bug fixes for our business there, I'll hang fire until 408 in
February 2009 I think...

--- In vantage@yahoogroups .com, Chris Thompson <chriselectrix@ ...>
wrote:
>
> Hi,
>
> Ive just been notified that .407 has been released (it was released
on 20th December).
>
> Thanks,
>
>
> CHRIS
>
>
>
>
> ____________ _________ _________ __
> From: Chris Thompson <chriselectrix@ ...>
> To: vantage@yahoogroups .com
> Sent: Thursday, December 18, 2008 3:43:15 PM
> Subject: Re: [Vantage] Re: 407 ETA
>
>
> Jonathan,
>
> When you had the problem with the wiping of the Primary Bins, how
did you resolve it?
>
> Has anybody else had this problem from upgrading to 406a?
>
> We are only on 404 and Epicor are doing some customisation for us
but we need to be on 407 - That'll be fun by the sounds of things!
>
> Cheers,
>
> CHRIS
>
> ____________ _________ _________ __
> From: Jonathan Lang <lsbestinc@yahoo. com>
> To: vantage@yahoogroups .com
> Sent: Wednesday, December 17, 2008 5:29:03 PM
> Subject: RE: [Vantage] Re: 407 ETA
>
> Mark,
> Â
> Notice the 9.."x". I'll wait for a later version of the kernel
before upgrading. Everytime upgrades come out that fixes a problem I
have, I cringe wondering what chaos the patch will unleash on my DB.
> Â
> I did upgrade to 406A because it fixed a HUGE problem with Job
Closing. After the upgrade was finished I noticed that all of the
Primary Bins had been erased from many parts, not all. When I ran a
report to see how many parts had no Primary Bin it counted 19,056
parts.
> Â
> There were many other "little" problems I had to fix, but you are
left with a queezy feeling after the upgrade has been accomplished.
> Jonathan LangÂ
> Oil Rite Corporation
> Sr. Network Administrator
> Ph: (920) 682-6173 Ext: 126
> Fax: (920) 682-7699
> jlang@oilrite. com
>
> --- On Wed, 12/17/08, Mark Wonsil <mark_wonsil@ yahoo.com> wrote:
>
> From: Mark Wonsil <mark_wonsil@ yahoo.com>
> Subject: RE: [Vantage] Re: 407 ETA
> To: vantage@yahoogroups .com
> Date: Wednesday, December 17, 2008, 9:53 AM
>
> >
> > Every release brings that many more problems. I'll wait for 9.x.
> >
>
> Oh, Dude...
>
> Mark "with open issues on 9" W.
>
> [Non-text portions of this message have been removed]
>
> [Non-text portions of this message have been removed]
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>

[Non-text portions of this message have been removed]