Subassembly and Scheduling

Epicor will backward schedule until it hits today, then it will forward schedule from today IF you have "do not allow dates in the past" checked (which is logical).  Try raising the priority and it will schedule ahead of other jobs in the time frame you want.


Georgia 



---In vantage@yahoogroups.com, <scottyk537@...> wrote:

How much time is you sub assembly being scheduled? You will see this scenario if the part is not configured correctly and cannot make the due date because the sub assembly takes too much time. Try setting the due date on the job to sometime next year and reschedule.
 
Scott


On Fri, Oct 4, 2013 at 1:56 PM, <nhoyt111@...> wrote:

 
<div>
  
  
  <p>&nbsp;No, that&#39;s the kicker.&nbsp; I have 4 on hand.<var></var></p>


---In vantage@yahoogroups.com, <vantage@yahoogroups.com> wrote:

Is there an expected receipt date for a material used to make anything in that subassembly?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of nhoyt111@...
Sent: Friday, October 04, 2013 1:29 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Subassembly and Scheduling



Good Afternoon,



We are trying to start using the scheduling engine in 9.05.607B. I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled. The only way this doesn't happen is if I manually reschedule and override material constraints. this isn't a stock part, so I wouldn't even think that material constraint would come into account.



Has anyone worked with scheduling and assemblies and come up with a method that works? Has anyone discovered any bug in this area?



Thanks very much,

nancy



[Non-text portions of this message have been removed]
</div>
 


<div style="color:rgb(255,255,255);min-height:0px;"></div>

Good Afternoon,

 

We are trying to start using the scheduling engine in 9.05.607B.  I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled.  The only way this doesn't happen is if I manually reschedule and override material constraints.  this isn't a stock part, so I wouldn't even think that material constraint would come into account.

 

Has anyone worked with scheduling and assemblies and come up with a method that works?  Has anyone discovered any  bug in this area?

 

Thanks very much,

nancy

Is there an expected receipt date for a material used to make anything in that subassembly?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of nhoyt111@...
Sent: Friday, October 04, 2013 1:29 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Subassembly and Scheduling



Good Afternoon,



We are trying to start using the scheduling engine in 9.05.607B. I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled. The only way this doesn't happen is if I manually reschedule and override material constraints. this isn't a stock part, so I wouldn't even think that material constraint would come into account.



Has anyone worked with scheduling and assemblies and come up with a method that works? Has anyone discovered any bug in this area?



Thanks very much,

nancy



[Non-text portions of this message have been removed]

 No, that's the kicker.  I have 4 on hand.



---In vantage@yahoogroups.com, <vantage@yahoogroups.com> wrote:

Is there an expected receipt date for a material used to make anything in that subassembly?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of nhoyt111@...
Sent: Friday, October 04, 2013 1:29 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Subassembly and Scheduling



Good Afternoon,



We are trying to start using the scheduling engine in 9.05.607B. I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled. The only way this doesn't happen is if I manually reschedule and override material constraints. this isn't a stock part, so I wouldn't even think that material constraint would come into account.



Has anyone worked with scheduling and assemblies and come up with a method that works? Has anyone discovered any bug in this area?



Thanks very much,

nancy



[Non-text portions of this message have been removed]
And just to be sure, that on hand qty exceeds demand for entire company? Just on a hunch, try changing job scheduling priority code to one that doesn’t have the minimize wip checked as true then reschedule. Are you moving this thru the Job Scheduling board?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of nhoyt111@...
Sent: Friday, October 04, 2013 1:56 PM
To: vantage@yahoogroups.com
Subject: RE: RE: [Vantage] Subassembly and Scheduling



No, that's the kicker. I have 4 on hand.


---In vantage@yahoogroups.com, <vantage@yahoogroups.com> wrote:
Is there an expected receipt date for a material used to make anything in that subassembly?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...<mailto:1.234354861@...>]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com<mailto:vantage@yahoogroups.com> [mailto:vantage@yahoogroups.com<mailto:vantage@yahoogroups.com>] On Behalf Of nhoyt111@...<mailto:nhoyt111@...>
Sent: Friday, October 04, 2013 1:29 PM
To: vantage@yahoogroups.com<mailto:vantage@yahoogroups.com>
Subject: [Vantage] Subassembly and Scheduling



Good Afternoon,



We are trying to start using the scheduling engine in 9.05.607B. I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled. The only way this doesn't happen is if I manually reschedule and override material constraints. this isn't a stock part, so I wouldn't even think that material constraint would come into account.



Has anyone worked with scheduling and assemblies and come up with a method that works? Has anyone discovered any bug in this area?



Thanks very much,

nancy



[Non-text portions of this message have been removed]



[Non-text portions of this message have been removed]
How much time is you sub assembly being scheduled? You will see this scenario if the part is not configured correctly and cannot make the due date because the sub assembly takes too much time. Try setting the due date on the job to sometime next year and reschedule.
Â
Scott


On Fri, Oct 4, 2013 at 1:56 PM, <nhoyt111@...> wrote:

Â
<div>
  
  
  <p><p> No, that&#39;s the kicker.  I have 4 on hand.<var></var></p>


---In vantage@yahoogroups.com, <vantage@yahoogroups.com> wrote:

Is there an expected receipt date for a material used to make anything in that subassembly?

Rob Bucek
Production Control Manager
PH: (715) 284-5376 ext 311
Mobile: (715)896-4832
FAX: (715)284-4084
[cid:1.234354861@...]<http://www.dsmfg.com/>
(Click the logo to view our site)<http://www.dsmfg.com/>

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of nhoyt111@...
Sent: Friday, October 04, 2013 1:29 PM
To: vantage@yahoogroups.com
Subject: [Vantage] Subassembly and Scheduling



Good Afternoon,



We are trying to start using the scheduling engine in 9.05.607B. I am finding that where we have a subassembly and I run for backwards scheduling, the subassembly gets forward scheduled from today and then the rest of the operations backwards scheduled. The only way this doesn't happen is if I manually reschedule and override material constraints. this isn't a stock part, so I wouldn't even think that material constraint would come into account.



Has anyone worked with scheduling and assemblies and come up with a method that works? Has anyone discovered any bug in this area?



Thanks very much,

nancy



[Non-text portions of this message have been removed]